Override - Parcel Holds | | | 12/18/2013 | | |
|
|
|
|
CHANGE STATUS TO (FNL) | | | 12/18/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
I spoke with Bill Vandegrift at the direction of Jason Blais. Bill said to close this permit as each of the tenat spaces and other mechanical permits have been completed in the structure completing all of the required work and corrections. 12/17/13 ajs
|
DOC - Permit Expired | 1/22/2001 | 1/22/2001 | 1/22/2001 | P | PASS |
Alan Hauser
|
|
|
Added by Inspector: 350 On 1/22/2001 12:48:32 PM
|
INSP - Final | 8/13/1998 | 8/13/1998 | 8/13/1998 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - not ready for final, no gas piping, and finish condensate at
|
INSP - Final | 8/13/1998 | 8/13/1998 | 8/13/1998 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - not ready for final, no gas piping, and finish condensate at
|
INSP - Final | 8/4/1998 | 8/5/1998 | 8/5/1998 | A | FAIL |
Alan Hauser
|
|
|
08/05/98 350 - no r/i inspections, all tile in and work covered, asked r site with ladder for inspection
|
INSP - Final | 8/4/1998 | 8/5/1998 | 8/5/1998 | A | FAIL |
Alan Hauser
|
|
|
08/05/98 350 - no r/i inspections, all tile in and work covered, asked r site with ladder for inspection
|
Receive PAYMENT IN FULL | | | 8/5/1998 | | |
|
|
|
|
Fee Due (change status F) | | | 7/29/1998 | | |
|
|
|
ADDITIONAL JOB VALUE
|
(F) Reprint permit | | | 7/29/1998 | | |
|
|
|
|
INSP - Final | 7/6/1998 | 7/7/1998 | 7/7/1998 | A | PASS |
Alan Hauser
|
|
|
07/07/98 350 - two test ok, 60# test
|
INSP - Final | 7/6/1998 | 7/7/1998 | 7/7/1998 | A | PASS |
Alan Hauser
|
|
|
07/07/98 350 - two test ok, 60# test
|
INSP - Framing/ Rough-in | 7/1/1998 | 7/2/1998 | 7/2/1998 | A | FAIL |
Alan Hauser
|
|
|
07/02/98 350 - no access to roof, correction on comb. air to pool htrs.
|
INSP - Final | 6/15/1998 | 6/15/1998 | 6/15/1998 | P | PART |
Alan Hauser
|
|
|
06/15/98 350 - pt ok for boiler room piping
|
INSP - Final | 6/15/1998 | 6/15/1998 | 6/15/1998 | P | PART |
Alan Hauser
|
|
|
06/15/98 350 - pt ok for boiler room piping
|
INSP - Framing/ Rough-in | 6/11/1998 | 6/12/1998 | 6/12/1998 | A | PART |
Alan Hauser
|
|
|
06/12/98 350 - GAS TEST ONLY--ROBYN ###-#### pt on 2# piping only, still need test on low pressure side and there is combustion air to equipment room
|
INSP - Framing/ Rough-in | 6/10/1998 | 6/11/1998 | 6/11/1998 | A | PART |
Alan Hauser
|
|
|
06/11/98 350 - this is for shell/core only, only 9 r.t.u looked at. gas to be on each tenant improvement. signed temp. on shell
|
(F) Reprint permit | | | 6/8/1998 | | |
|
|
|
|
Receive PAYMENT IN FULL | | | 3/26/1998 | | |
|
|
|
|
Application received | | | 3/24/1998 | | |
|
|
|
|
Issue & PRINT FEE-DUE permit | | | 3/24/1998 | | |
|
|
|
|