Final | 1/4/2000 | 1/4/2000 | 1/4/2000 | P | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 01/04/2000 at 10:10:36. Contact: ###-####.
|
Final | 1/3/2000 | 1/3/2000 | 1/3/2000 | P | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 01/03/2000 at 09:42:50. Contact: ###-####. Not ready called Sandy.
|
Receive PAYMENT IN FULL | | | 12/15/1999 | | DONE |
|
|
|
|
Rough-in | 11/18/1999 | 11/18/1999 | 11/17/1999 | P | PASS |
Dixie Fellows
|
|
|
R/I ok.
|
Pressure Test | 11/18/1999 | 11/18/1999 | 11/17/1999 | P | PASS |
Dixie Fellows
|
|
|
Gas ok.
|
Rough-in | 11/17/1999 | 11/17/1999 | 11/17/1999 | P | FAIL |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 11/17/1999 at 08:33:14. Contact: ###-####. Done #411.
|
Pressure Test | 11/17/1999 | 11/17/1999 | 11/17/1999 | P | FAIL |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 11/17/1999 at 08:33:40. Contact: ###-####. Done #411.
|
Application received | | | 11/10/1999 | | |
|
|
|
|
Issue & PRINT FEE-DUE permit | | | 11/10/1999 | | DONE |
|
|
|
|