MIS-Aging Inspection | 5/8/2019 | 5/8/2019 | 5/8/2019 | | DONE |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 5/8/2019 | 5/8/2019 | 5/8/2019 | P | PASS |
Jim Storey
|
|
|
|
MEC-Final | 8/20/2018 | 8/20/2018 | 8/20/2018 | P | PASS |
Jack Reynolds
|
|
|
cryo bank ok
|
MEC-Conference | 7/3/2018 | 7/3/2018 | 7/3/2018 | P | DONE |
Jack Reynolds
|
|
|
Met with Justin to look at the basement where the cryo bank is located. Seeing the size of the bank and reviewing the mechanical codes I see no reason for a mechanical permit to be pulled on this project. The nitrogen storage is under the max capacity and no class 3 or 4 materials are being stored at this time. Justin is going to email me the material data sheets aswell.
|
MEC-Conference | 6/29/2018 | 7/2/2018 | 7/2/2018 | A | CANC |
Jack Reynolds
|
|
|
monday early afternoon - cancelled Justin didnt answer phone call so i left him a message
|
MEC-Conference | 6/27/2018 | 6/29/2018 | 6/29/2018 | P | CANC |
Jack Reynolds
|
|
|
talked with Justin about access to building early afternoon friday- call 20 mins ahead-###-#### Justin ; Phone #: ###-####- talked with Justin will reschedule for monday afternoon
|
MEC-Conference | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PEND |
Jack Reynolds
|
|
|
Per Jim Page Phone #: ###-####- no access- called Justin to find out more information on the cryo banks in the basement to find out whats being stored in them
|
Application received | | | 6/27/2018 | | |
|
|
|
|
Issue Misc Permit............ | | | 6/27/2018 | | DONE |
|
|
|
|