INSP-Final | 10/2/2014 | 10/3/2014 | 10/3/2014 | A | PASS |
Craig D. Hanson
|
|
|
System conected and in service. General contractor to repair penatrations in draft stop.
|
INSP-Sprinkler Rough-in/Hydro | 9/24/2014 | 9/25/2014 | 9/25/2014 | A | CANC |
Craig D. Hanson
|
|
|
|
INSP-Sprinkler Rough-in | 8/8/2014 | 8/11/2014 | 8/11/2014 | A | PASS |
Troy Cobbley
|
|
|
1st floor branch line restraints have been installed. Piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 8/8/2014 | 8/8/2014 | 8/8/2014 | P | PART |
Troy Cobbley
|
|
|
Upper level/second floor piping is ok to cover. Can not cover the lower level piping untill a re-inspection verifies that seismic bracing on the branchlines has been completed.
|
Sprinkler Plan Check | 8/5/2014 | | 8/5/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/5/2014 | | DONE |
Tim Frost
|
|
|
|
Issue and Courier | | | 8/5/2014 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 8/1/2014 | | DONE |
Christina Prado
|
|
|
Received four sets of revised sheet 3 of 3 - Attic Plan;Plans stamped and taken to Tim Frost for review
|
Plan resubmittals received | | | 7/31/2014 | | DONE |
Christina Prado
|
|
|
Received four sets of revised sheet 3 of 3 - Attic Plan;Plans stamped and taken to Tim Frost for review
|
Plan resubmittals received | | | 7/28/2014 | | DONE |
Christina Prado
|
|
|
received one cover letter, one response letter and 4 sets of revised plan sheets marked sheet 3 of 3 attic plan;plans taken to Tim Frost for review
|
Telephone call | | | 7/28/2014 | | DONE |
|
|
|
Called Don and left him a message the sprinklers in the attice were over spaced. I asked him to email me a new set of drawings.
Wrote a follow up email to Jacci today. 7/30/2014
|
Sprinkler Plan Check | 7/23/2014 | | 7/23/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 7/23/2014 | | FAIL |
|
|
|
Sent contractor failed review.
|
Plan resubmittals received | | | 7/11/2014 | | DONE |
Christina Prado
|
|
|
Received four revised sets of plans and calcs; Plans taken to TIm Frost for further review
|
Sprinkler Plan Check | 6/30/2014 | | 6/30/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 6/30/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/30/2014 | | DONE |
|
|
|
Sent email to contractor.
|
Application received | | | 6/24/2014 | | |
|
|
|
|
Plan assigned to (Tim) | 6/24/2014 | | | | |
Tim Frost
|
|
|
|