INSP-Final | 8/6/2015 | 8/6/2015 | 8/6/2015 | P | PASS |
Katie Marron
|
|
|
Previous tank and pump correction items satisfactorily completed. Flow test complete. Scope of work completed satisfactorily. Permit Finaled.
|
INSP-Final | 7/31/2015 | 8/3/2015 | 8/3/2015 | P | NR |
Katie Marron
|
|
|
Per call with Anthony still waiting on plumbing contracto to install water spigot to sprinkler tank.
|
INSP-Final | 7/31/2015 | 7/31/2015 | 7/31/2015 | P | CANC |
Troy Cobbley
|
|
|
Call Anthony when you are headed that way. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Final | 7/28/2015 | 7/29/2015 | 7/29/2015 | P | CANC |
Thomas Walsh
|
|
|
Not ready for inspection. Tank fill line not completed and pump not pre-tested yet. Will reschedule when these items are conpleted.
|
INSP-Sprinkler Rough-in | 6/1/2015 | 6/4/2015 | 6/4/2015 | P | PASS |
Katie Marron
|
|
|
Tenting completed satisfactory. One spot in middle bedroom, 1st flr identified as needing minor adjustments to tighten down insulation on side of pipe..
|
INSP-Sprinkler Rough-in | 6/1/2015 | 6/1/2015 | 6/1/2015 | P | CANC |
Katie Marron
|
|
|
Tenting inspection -please try to come later in the day if possible. Call Anthony with questions. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 4/21/2015 | 4/21/2015 | 4/21/2015 | A | PART |
Katie Marron
|
|
|
Scope of work good to tent with the following exceptions. Heads are missing in mud room and over water heater closet on first floor, per plan. Provide heads or justification for exception according to NFPA 13D. **Per phone discussion with Anthony, hallway head provides exceptable coverage to mudroom in accordance with NFPA 13D 8.2. Additionally water heater is no longer located in that closet so head no longer required since space is less than 24 sqft per chapter 6.
Items remaining, tank requires hose bib to main water supply and flow switch to be tested once hooked into alarm system NACFR 2008-013
|
Sprinkler Plan Check | 12/19/2014 | | 12/19/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/19/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/19/2014 | | DONE |
|
|
|
|
Issue and Courier | | | 12/19/2014 | | DONE |
Candy A. Nichols
|
|
|
emailed Shelley that permit is on it's way to her, customer was not called
|
Plan resubmittals received | | | 12/10/2014 | | DONE |
Candy A. Nichols
|
|
|
plan mod submitted-received 4 sets of each sheet FP1 & FP2, 2 each set of sheets hydro calcs, 4 Talco fire system hydrant calcs-put in Lee Meredith's cubby
|
Plan assigned to (Tim) | 10/29/2014 | | 10/29/2014 | | DONE |
Tim Frost
|
|
|
|
1st review completed | | | 10/29/2014 | | PASS |
|
|
|
|
Sprinkler Plan Check | 10/29/2014 | | 10/29/2014 | | PASS |
Tim Frost
|
|
|
|
Miscellaneous action | | | 10/29/2014 | | DONE |
|
|
|
Sending back to NACFR 10/29/2014
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/29/2014 | | DONE |
|
|
|
|
Issue and Courier | | | 10/29/2014 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 10/23/2014 | | |
|
|
|
|
Plan assigned to (Lee) | 10/23/2014 | | | | |
Tim Frost
|
|
|
|