INSP-Final | 11/16/2015 | 11/16/2015 | 11/16/2015 | P | PASS |
Katie Marron
|
|
|
Flow test of unit 3596 completed satisfactory. Modifications by contractor were performed on sight to flow switch to achieve successful test. Scope of work complete, permit finaled.
|
INSP-Final | 10/2/2015 | 10/6/2015 | 10/6/2015 | A | PART |
Katie Marron
|
|
|
Final inspection completed satisfactory for unit 3600. Initial issue with flow switch was corrected on site.
Second unit walk through complete, just need to flow test.
|
INSP-Sprinkler Rough-in/Hydro | 7/15/2015 | 7/16/2015 | 7/15/2015 | A | PASS |
Katie Marron
|
|
|
Inspection completed on 7/15/15 per contractor request. Hydro static retest of left townhome fire sprinkler system pass. Tenting at third floor for both town homes OK at time of inspection.
|
INSP-Sprinkler Rough-in/Hydro | 7/13/2015 | 7/14/2015 | 7/14/2015 | A | PART |
Katie Marron
|
|
|
When looking at the townhomes, the one to the right passed the hydro. The system for the left townhouse failed: dropped 5 psi over 2 hrs. Leak could not be readily found.
Supply line in still to be corrected to 1 1/4".
|
Plan assigned to (Tim) | 7/10/2015 | | 7/10/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/10/2015 | | 7/10/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/10/2015 | | DONE |
|
|
|
|
Issue and Courier | | | 7/10/2015 | | DONE |
|
|
|
plan mod-as per Lee-2hours @ $50.00 each hour-sent to North Ada Colunty
|
Plan resubmittals received | | | 7/8/2015 | | DONE |
|
|
|
plan mod recieved-4 sets of FP1, FP2, as built /revision cover, GC response letter, 4 hydraulic calcs & tyco rapid response series LF!! residential-took to Tim Frost
|
INSP-Sprinkler Rough-in | 7/6/2015 | 7/6/2015 | 7/6/2015 | A | PART |
Katie Marron
|
|
|
Rough in complete pending resubmittal approval. Following items need to be correctd: supply line into base of riser to be corrected to 1 1/4" instead of 1". Riser in unit 3600 missing flow switch.
|
Plan assigned to (Craig) | 10/30/2014 | | 10/30/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/30/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/30/2014 | | DONE |
Tim Frost
|
|
|
|
Issue and Courier | | | 10/30/2014 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 10/27/2014 | | |
|
|
|
|
Plan assigned to (Lee) | 10/27/2014 | | | | |
Lee G Meredith
|
|
|
|