Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberNAF14-00028
StatusFinaled
Name TRIBAL FIRE SYSTEMS
Site Address 415 E 42ND ST
Project NameTRAILWINDS APARTMENT
Customer Number 
ePlanReviewNo
Description
Tribal Fire Systems will install approximately 8”x 51’ of C-900 underground fire protection piping with associated fittings and thrust blocks.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final6/6/20166/6/20166/6/2016PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro5/7/20155/8/20155/8/2015PPASS
DetailsTroy Cobbley
Underground hydro test passed
INSP-Sprinkler Rough-in/Hydro5/5/20155/6/20155/6/2015AFAIL
DetailsTroy Cobbley
Hydro Underground failded due to visible leak at guage
INSP-Sprinkler Rough-in/Hydro5/4/20155/5/20155/5/2015ACANC
DetailsTroy Cobbley
Wrong permit number called in.
INSP-Supply line flush4/6/20154/7/20154/8/2015APASS
DetailsTim Frost
Passed flush
Plan resubmittals received  1/21/2015 DONE
DetailsCandy A. Nichols
plan mods received-4 sets of each-FP1, FP2, FP3, FP4, HYDRAULIC CALC #1 3RD FLOOR, seismic bracing calc, material data submittals took to Tim Frost
INSP-Sprinkler Rough-in/Hydro1/12/20151/13/20151/13/2015APASS
DetailsTroy Cobbley
Remaining underground piping is ok to cover.
INSP-Sprinkler Rough-in/Hydro1/8/20151/9/20151/9/2015PPASS
DetailsTroy Cobbley
The underground supply piping up to the bottom of the DI is ok to bury.
INSP-Sprinkler Rough-in1/8/20151/9/20151/8/2015APASS
DetailsTroy Cobbley
Piping from the hot tap to 20'-0" ok for cover. Additional fittings have been installed that will need to be accounted for in the hydraulic calculations.
INSP-Sprinkler Rough-in1/7/20151/7/20151/7/2015PFAIL
DetailsTroy Cobbley
Piping that had been previously buried has been removed. No new piping has been installed yet due to contractor (not applicant) waiting for a "road box" to continue installation. Tribal Fire was going to stop at project site and verify installation.
INSP-Sprinkler Rough-in12/22/201412/23/201412/23/2014AFAIL
DetailsTroy Cobbley
Inspection turned into conference since the piping installed in the trench does not meet the minimum 4'6" bury requirement. Piping needs to be installed at the correct depth and inspected for approval to cover which will include thrust blocks.
CHANGE STATUS TO (ISS)  12/22/2014 DONE
DetailsCandy A. Nichols
Plan assigned to (Tim)12/19/2014 12/19/2014 DONE
DetailsTim Frost
Sprinkler Plan Check12/19/2014 12/19/2014 PASS
DetailsTim Frost
1st review completed  12/19/2014 PASS
PLANS/APPL TAKEN TO FRONT DESK  12/19/2014 DONE
Issue and Courier  12/19/2014 DONE
DetailsCandy A. Nichols
sent an email to Shelley that plans were ready and coming her way
Application received  12/12/2014