INSP-Final | 3/16/2015 | 3/17/2015 | 3/17/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final | 3/13/2015 | 3/16/2015 | 3/16/2015 | A | FAIL |
Troy Cobbley
|
|
|
All of the canopies were missing from the sprinkler pendants and the shipping caps are still installed
|
INSP-Final | 3/13/2015 | 3/13/2015 | 3/13/2015 | P | CANC |
Troy Cobbley
|
|
|
Anthony is going to check project status prior to inspection. Rescheduled for monday
|
INSP-Final | 2/20/2015 | 2/25/2015 | 2/25/2015 | A | FAIL |
Troy Cobbley
|
|
|
No sheet rock/ceilings, no paint, no sprinkler canopies. No inspection performed.
|
INSP-Sprinkler Rough-in | 2/2/2015 | 2/3/2015 | 2/3/2015 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping ok to cover. I noted the annual inspection will be required prior to a final sign off.
|
INSP-Sprinkler Rough-in | 2/2/2015 | 2/2/2015 | 2/2/2015 | P | CANC |
Troy Cobbley
|
|
|
Please make this the last inspection of the day if possible. Thanks. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
1st review completed | | | 1/7/2015 | | PASS |
|
|
|
|
Sprinkler Plan Check | 1/7/2015 | | 1/7/2015 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 1/7/2015 | | 1/7/2015 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/7/2015 | | DONE |
|
|
|
|
Issue and Courier | | | 1/7/2015 | | DONE |
Candy A. Nichols
|
|
|
|