Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberNAF15-00006
StatusFinaled
Name TRIBAL FIRE SYSTEMS
Site Address 415 E 42ND ST
Project NameTRAILWINDS APARTMENT
Customer Number 
ePlanReviewNo
Description
[Trailwinds Apartments] – GCB14-00099 – BLD2014-00099
The fire sprinkler scope of work consists of a NFPA 13R fire sprinkler system protecting a three level building.

The underground supply is under permit NAF14-00028

Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final11/4/201511/4/201511/4/2015PPASS
DetailsKatie Marron
Fire life safety pass.

Riser room signage, map at annunciator with FACP and Riser Room call outs and map in FACP room verified.
INSP-Final11/2/201511/3/201511/4/2015PCANC
DetailsKatie Marron
Cancelled reschuduled for tomorrow.
INSP-Final10/29/201510/30/201510/30/2015ACANC
DetailsThomas Walsh
Fire sprinkler contractors not available to conduct inspection, including flow tests of the fire sprinkler risers.
INSP-Final9/30/201510/1/201510/1/2015APART
DetailsKatie Marron
Partial final complete for North East side. To be verified at full final, heads in bathroom changed to intermediate and one head in 2nd floor hallway @ north east side changed to intermediate due to proximity to heat device. Also flow test and forward flow to be tested.
INSP-Sprinkler Rough-in/Hydro9/30/20159/30/20159/30/2015PDONE
DetailsKatie Marron
All hydro tests have been previously completed. Walked through north east wing, identified painted heads to be replaced and heads in bathrooms that need to be changed to 175 deg due to proximity to heat source.

Previous item of concern with the unheated patio/storage area and sprinkler head. Contractor added a vent register between living space and patio storage area.
INSP-Final9/24/20159/25/20159/25/2015PCANC
DetailsKatie Marron
Per phone call with Clarence.
INSP-Sprinkler Rough-in/Hydro7/28/20157/28/20157/28/2015PFAIL
DetailsJim Page
Rough to cover inspection for area's on third floor, have concerns for exterior storage rooms no having adequate heat source to prevent freezing, needs to be repaired.
INSP-Sprinkler Rough-in/Hydro7/1/20157/2/20157/2/2015ACANC
DetailsKatie Marron
Wrong number provided. Went to site at 10am, no general or sprinkler contractor on site. Checked to see if any risers were pressurized for hydro, none were. Called previous contact and left a message, no call back.
INSP-Sprinkler Rough-in/Hydro6/24/20156/24/20156/24/2015PPASS
DetailsKatie Marron
Rough-in third floor southwest wing, ok for tenting. One plugged/missing head in hallway and one hangar not connected. 4 dummy heads are installed for sidewalls.

Hydro test for southwest wing 3rd floor pass.

Previous items not corrected yet.
**Riser room needs tenting inspection**
**Pay special attention to tenting for piping running through patio closet to sidewall**
INSP-Sprinkler Rough-in6/8/20156/9/20156/9/2015APART
DetailsKatie Marron
Ok to cover for wedge/corner common space at 1st, 2nd, 3rd flrs. Correction items: 1st flr- 1 missing sprinkler/overspaced area and 2 uninstalled corridor heads; 3rd flr- 5 uninstalled corridor heads. See notes on drawings.

Tenting of 1st floor small garage on north east end completed satisfactory.
INSP-Sprinkler Rough-in6/4/20156/4/20156/4/2015APART
DetailsKatie Marron
Tenting Inspection for 3rd floor, East wing. Netting was already hung in all but two rooms and blow in insulation process was beginning. One issue was spot corrected. Tenting satisfactory
INSP-Sprinkler Rough-in/Hydro5/27/20155/28/20155/28/2015PPASS
DetailsKatie Marron
3rd floor, North East Wing ok to cover and hydro pass. Does NOT include common area wedge, resubmitted plans were not on site.
INSP-Sprinkler Rough-in/Hydro5/13/20155/13/20155/13/2015PPASS
DetailsTroy Cobbley
See the city approved plans for locations where piping is ok to cover. Missing earth quake bracing on mains. Need tenting approved for the sidewalls out over the closets. 2nd floor hydro test passed.
INSP-Sprinkler Rough-in/Hydro5/7/20155/8/20155/8/2015PPASS
DetailsTroy Cobbley
Overhead hydro test of the first floor passed
INSP-Sprinkler Rough-in/Hydro5/5/20155/6/20155/6/2015AFAIL
DetailsTroy Cobbley
First floor hydro test failed due to visible loss on guage.
INSP-Sprinkler Rough-in/Hydro5/5/20155/5/20155/5/2015PPART
DetailsTroy Cobbley
First floor overhead hydro test failed. First floor rough-in passed for the most part. See the city approved plans for locations where piping is ok to cover as marked in red. Plan modifications are required due to pipe routing changes due to steel beams. The area where these changes are located can not be covered until the plan modifications have been approved.
Sprinkler Plan Check2/26/2015 2/26/2015 PASS
DetailsTim Frost
Plan assigned to (Tim)2/26/2015 2/26/2015 DONE
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  2/26/2015 DONE
Permit Ready to Issue  2/26/2015 DONE
Issue and Courier  2/26/2015 DONE
Early Start  2/23/2015 PASS
Plan resubmittals received  2/20/2015 DONE
DetailsCandy A. Nichols
resubmittals received-4 each sheet FP1, FP2, FP3, FP4, 4 each response letter, TFS material data submittals, hydro calcs #1 3rd floor, 4 more response letters-took to Tim Frost
Telephone call  2/17/2015 DONE
DetailsCandy A. Nichols
called Jess@ Tribal Fire Systems to let know-permit plan review failed and that I will be sending plans back to NAF
Sprinkler Plan Check2/13/2015 2/13/2015 FAIL
DetailsTim Frost
Plan resubmittals received  2/6/2015 DONE
DetailsCandy A. Nichols
resubmittals recieved: cover sheet from NAF, 4 sets material data submittal, 4 sets of description of submmittals,4 hydro calcs, 4 sets of sheets FP1, FP2, FP3, FP4-put in cubby for Tim Frost
1st review completed  1/29/2015 FAIL
DetailsTim Frost
Application received  1/26/2015  
Plan assigned to (Tim)1/26/2015    
DetailsTim Frost