INSP-Final | 3/27/2017 | 3/28/2017 | 3/28/2017 | P | PASS |
Katie Marron
|
|
|
Fire Life Safety Pass.
|
Plan assigned to (Scott) | 11/19/2015 | | 11/19/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/19/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/19/2015 | | DONE |
|
|
|
|
Issue and Courier | | | 11/19/2015 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/18/2015 | | DONE |
|
|
|
resubmittals received 1 response letter and 2 of each sheet A2.0, A2.2, A2.3, A4.0, A4.1 & A8.0-Took to Scott A
|
Plan assigned to (Scott) | 10/26/2015 | | 10/28/2015 | | FAIL |
Scott Arellano
|
|
|
Emailed architect plan review comments. Attached report to case.
|
1st review completed | | | 10/28/2015 | | FAIL |
|
|
|
|
Application received | | | 10/26/2015 | | |
Scott Arellano
|
|
|
Building
|