INSP-Final | 5/18/2017 | 5/19/2017 | 5/19/2017 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in | 11/28/2016 | 11/29/2016 | 11/29/2016 | P | CANC |
Katie Marron
|
|
|
Wrong permit. Inspection completed/recorded for Bldg A of same complex
|
INSP-Supply line flush | 8/11/2016 | 8/12/2016 | 8/12/2016 | P | PASS |
Katie Marron
|
|
|
Flush completed satisfatory.
|
INSP-Sprinkler Rough-in/Hydro | 6/21/2016 | 6/22/2016 | 6/22/2016 | P | PASS |
Katie Marron
|
|
|
Hydro static test completed satisfactory. Only flush remains.
|
INSP-Supply line flush | 6/21/2016 | 6/22/2016 | 6/22/2016 | P | CANC |
Katie Marron
|
|
|
Flush after hydro Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Sprinkler Rough-in | 5/5/2016 | 5/6/2016 | 5/6/2016 | P | PASS |
Katie Marron
|
|
|
Underground cover inspection completed satisfactory. Ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 5/5/2016 | 5/6/2016 | 5/6/2016 | P | CANC |
Katie Marron
|
|
|
No hydro today. Duplicate inspection for underground cover.
|
INSP-Sprinkler Rough-in | 1/5/2016 | 1/6/2016 | 1/6/2016 | A | PART |
Troy Cobbley
|
|
|
Underground supply line is ok to cover from tap to the sidewalk.
|
INSP-Sprinkler Rough-in | 1/5/2016 | 1/6/2016 | 1/5/2016 | A | FAIL |
Troy Cobbley
|
|
|
Minumum 4'6" bury dept not met.
|
1st review completed | | | 11/24/2015 | | PASS |
|
|
|
|
Sprinkler Plan Check | 11/24/2015 | | 11/24/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/24/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/24/2015 | | DONE |
|
|
|
permits had the plan review done and passed on 11/24/15-but were not changed to iss.
|
Issue and Courier | | | 11/24/2015 | | DONE |
|
|
|
permits had the plan review done and passed on 11/24/15-but were not changed to iss.
|
Application received | | | 11/20/2015 | | |
|
|
|
|
Plan assigned to (Tim) | 11/20/2015 | | | | |
Tim Frost
|
|
|
|