INSP-Final | 5/19/2016 | 5/20/2016 | 5/20/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 5/19/2016 | 5/20/2016 | 5/20/2016 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro passed
|
INSP-Sprinkler Rough-in/Hydro | 5/19/2016 | 5/19/2016 | 5/19/2016 | P | FAIL |
Troy Cobbley
|
|
|
Overhead hydro failed again due to loss of pressure
|
INSP-Sprinkler Rough-in/Hydro | 5/18/2016 | 5/19/2016 | 5/19/2016 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydro failed due to visible loss of pressure at the guage.
|
INSP-Sprinkler Rough-in/Hydro | 5/17/2016 | 5/18/2016 | 5/18/2016 | P | FAIL |
Troy Cobbley
|
|
|
Test failed due to a split valve. Rescheduled for tomorrow
|
INSP-Conference | 5/5/2016 | 5/6/2016 | 5/6/2016 | A | DONE |
Katie Marron
|
|
|
Discussed requirements for occupancy with Mike (superintendent).
|
Miscellaneous action | | | 4/15/2016 | | PASS |
|
|
|
Veified the hydraulic are still adequate, even with the additional sprinkler added to the end of the most remote branch line.
|
INSP-Sprinkler Rough-in | 4/14/2016 | 4/14/2016 | 4/14/2016 | P | PEND |
Katie Marron
|
|
|
Rough-in inspection completed. Verified all uprights and pendant drops. One hangar missing see plans on site. Hangar will be visible at final from drop ceiling. OK to cover PENDING resubmitted calcs for remote area 2 due to two sprinkler heads added to the calc area.
|
INSP-Sprinkler Rough-in | 3/31/2016 | 4/1/2016 | 4/1/2016 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled, point of contact on job could not get a set of approved resubmittal blue prints to have for inspection. Contractor will reschedule inspection for later date.
|
Plan assigned to (Tim) | 3/31/2016 | | 3/31/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/31/2016 | | 3/31/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/31/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/31/2016 | | DONE |
|
|
|
as per Tim F-plan mod is for a 2 hour plan review-sent to Shelley thru inner office mail
|
Plan resubmittals received | | | 3/25/2016 | | DONE |
|
|
|
3rd resubmittal recieved 4 of each-permit app, cover sheet,tyco report & sheet FP-1-set in cubby for Tim F
|
INSP-Sprinkler Rough-in | 3/21/2016 | 3/22/2016 | 3/22/2016 | P | FAIL |
Troy Cobbley
|
|
|
Plan modifications needed due to extensive changes needed such as adding upright sprinkler coverage that is missing is some locations and additional fittings have been added in the mains and riser nipples.
|
Sprinkler Plan Check | 12/23/2015 | | 12/23/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/23/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/23/2015 | | DONE |
|
|
|
|
Issue and Courier | | | 12/23/2015 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/22/2015 | | DONE |
|
|
|
resubmittals received 3 sets of sheet FP, 6 tyco manuals, 6 hydra calcs, 6 seismic bracing calcs, 3 GC letters& 3 owners info certs-put in fire cubby for Tim F
|
Telephone call | | | 12/3/2015 | | DONE |
|
|
|
called Shilo to let know plan review failed and the permit is on it's way back to North Ada County
|
Sprinkler Plan Check | 12/2/2015 | | 12/2/2015 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 12/2/2015 | | FAIL |
|
|
|
|
Application received | | | 11/24/2015 | | |
|
|
|
|
Plan assigned to (Tim) | 11/24/2015 | | | | |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 3/25/2016 | | | | |
Tim Frost
|
|
|
|