INSP-Final | 1/13/2017 | 1/17/2017 | 1/17/2017 | P | PASS |
Katie Marron
|
|
|
Building inspector to verify address numbers. Discussed placement options with contractor. Life Safety Pass.
|
INSP-Sprinkler Rough-in/Hydro | 1/13/2017 | 1/17/2017 | 1/17/2017 | P | CANC |
Katie Marron
|
|
|
Wrong/duplicate inspection type.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/13/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/13/2017 | | DONE |
|
|
|
|
Issue and Courier | | | 1/13/2017 | | DONE |
|
|
|
|
Plan assigned to (Katie) | 11/1/2016 | | 11/2/2016 | | PASS |
Katie Marron
|
|
|
Plan modification to remove fire alarm designation from cover sheet. It is not required for this structure. Walls were added to create some additional offices as well.
|
Plan resubmittals received | | | 11/1/2016 | | |
|
|
|
|
Plan assigned to (Katie) | 4/28/2016 | | 4/28/2016 | | PASS |
Katie Marron
|
|
|
Only resubmitted drawing sheets were provided, no cover sheet was provided for signature.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/28/2016 | | |
|
|
|
|
Override - Parcel Holds | | | 4/28/2016 | | |
|
|
|
|
Override - Parcel Holds | | | 4/28/2016 | | |
|
|
|
|
Permit Ready to Issue | | | 4/28/2016 | | DONE |
|
|
|
|
Issue and Courier | | | 4/28/2016 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/27/2016 | | DONE |
|
|
|
resubmittals received 2 sets of sheet A2.2 & GC checklist-took to Scott A
|
Telephone call | | | 4/18/2016 | | DONE |
Katie Marron
|
|
|
Spoke with Curt Barber regarding resubmittal items for Fire Code plan review and emailed Curt the Fire Code plan review report. Clint mentioned that Garden City Water Department may have sent us the requested Fire Flow documentation, however, I instructed Curtt to have this document submitted to Garden City and then routed back to Boise City with the additional revised building plan sheets so all revised information stays together. Instructions are outlined on Fire Code plan review report.
|
1st review completed | | | 2/19/2016 | | FAIL |
|
|
|
|
Plan assigned to (Scott) | 2/18/2016 | | 2/19/2016 | | FAIL |
Scott Arellano
|
|
|
Report attached to plans and emailed to architect.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/19/2016 | | |
|
|
|
|
Application DENIED | | | 2/19/2016 | | DONE |
|
|
|
plans failed so sent back to NACFR-sent email to Shelley
|
CHANGE STATUS TO (REV) | | | 2/19/2016 | | DONE |
|
|
|
was changed to final by mistake-plans failed so sent back to NACFR-emailed Shelley
|
Application received | | | 2/18/2016 | | |
|
|
|
|