INSP-Final | 12/19/2016 | 12/19/2016 | 12/19/2016 | P | PASS |
Katie Marron
|
|
|
Verified dry pendant, upright over cooler and escutcheons. Scope of work complete. Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 10/31/2016 | 11/1/2016 | 11/1/2016 | P | PART |
Katie Marron
|
|
|
No hydro required. Roughin for branch lines and uprights completed. Two uprights added at end of each branch line due to cross beam obstruction. **Dry pendant and one up wet pendant not installed at freezer area; freezer not installed one drop is provided**
|
Plan assigned to (Tim) | 9/8/2016 | | 9/8/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/8/2016 | | 9/8/2016 | | PASS |
Tim Frost
|
|
|
|
1st review completed | | | 9/8/2016 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/8/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/8/2016 | | DONE |
|
|
|
|
Issue and Courier | | | 9/8/2016 | | DONE |
|
|
|
put in inner office mail and emailed Shelley
|
Application received | | | 9/6/2016 | | |
|
|
|
|
Plan assigned to (Tim) | 9/6/2016 | | | | |
Tim Frost
|
|
|
|