Permit Information
Permit NumberNAF16-00057
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 5870 N GLENWOOD
Project NameADA COUNTY PARAMEDICS
Customer Number 
ePlanReviewNo
Description
[ADA County Paramedics]
The fire sprinkler scope of work consists of a one level building with an attic protected with a NFPA 13 system. The attic is a dry system with a steeply pitched roof. The bottom level is a combination light and ordinary hazard 1 system. There is 6” underground with a 4” riser and 4” backflow preventer. The dry system is 4” and the wet system is 3”. The wet system layout is a tree and the dry system is a loop.

The underground piping is under permit NAF16-00055
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final11/21/201611/22/201611/22/2016APASS
DetailsKatie Marron
24 Hr Air Test completed satisfactory. Phone #: ###-####
INSP-Sprinkler Rough-in11/17/201611/21/201611/21/2016APART
DetailsKatie Marron
24 air test began at 9:40 am on 11/21/16. Pressure was 42psi
INSP-Sprinkler Rough-in/Hydro11/17/201611/17/201611/17/2016APASS
DetailsKatie Marron
Hydrostatic test of FDC, Dry system and Wet system completed satisfactory.

24 hr air test still needed for dry system.
INSP-Sprinkler Rough-in/Hydro11/16/201611/16/201611/16/2016PFAIL
DetailsKatie Marron
Hydro was not able to be completed as Riser room was locked upon return after 2 hour period.
INSP-Sprinkler Rough-in/Hydro11/14/201611/15/201611/15/2016AFAIL
DetailsTroy Cobbley
Overhead hydro tests failed due to visible leak on the ground and pressure loss at the guages. I also noted that the supply piping to the FDC needs hydro tested.
INSP-Sprinkler Rough-in/Hydro11/14/201611/14/201611/14/2016PCANC
DetailsTroy Cobbley
Not ready for hydro test due to leak.

Please Contact Perly Daniels 30 minutes before inspection Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in11/9/201611/10/201611/10/2016PPART
DetailsKatie Marron
Rough in for dry and wet system completed. Grid areas ok to cover.
Correction item: Per note on plans earthquake bracing into wood shall be through bolted, contractor to correct and provide verification (photos).
Permit Ready to Issue  11/8/2016 DONE
CHANGE STATUS TO (ISS)  11/8/2016 DONE
plan mod ready-emailed
Shelley and put in inner office mail
Plan resubmittals received  11/7/2016 DONE
plan mod received 7 sets of fire sprinkler hydraulic design-took to Tim F
Plan resubmittals received  11/4/2016 DONE
plan mod recevied 4 sets of apps fire sprinkler hydraulic design, calcs, sheets FP1, FP2, FP3- took to Scott Arellano
INSP-Sprinkler Rough-in/Hydro10/26/201610/27/201610/27/2016AFAIL
DetailsTroy Cobbley
Stopped rough-in inspection on the dry system due to pipe routing changes including in the remote area. Stopped the rough-in inspection on the wet system due to pipe routing changes in the main that effects the remote area. I also noted a branchline size the did not match plan. Plans need to be re-submitted showing all pipe routing changes. Fitter is using 1/2 lag bolts in the bottom of the 2x6 structure. I need to verify that is ok.
PLANS/APPL TAKEN TO FRONT DESK  10/12/2016 DONE
DetailsTim Frost
Sprinkler Plan Check10/12/2016 10/12/2016 PASS
DetailsTim Frost
Permit Ready to Issue  10/12/2016 DONE
Issue and Courier  10/12/2016 DONE
sent email to Shelley that it was coming her way thru inner office mail
Plan resubmittals received  10/11/2016 DONE
resubmittals received 3 sets of FP1, FP2 & FP3-as well as all the fire flow info, sprinkler info, fittings etc-put in cubby for Tim Frost
Miscellaneous action  10/10/2016 DONE
Called the contractor on Friday and left a message to call me. I wrote them and email today and asked them to call me.

The did not include any small documents.
They redesign the sprinkler layout in the apparatus bay to OH 1 but did not revise the calculations to OH 1.

In order to expedite the project I am going to ask them to bring the submittal directly to me.
Plan resubmittals received  10/7/2016 DONE
resubmittals received-put in cubby for Tim Frost
Telephone call  9/29/2016 DONE
emailed Shelley that plans fialed and are being sent back to her thru inner office mail
Plan resubmittals received  9/22/2016 DONE
resubmittals received 4 sets of drawings-put in cubby for Tim Frost
Application DENIED  9/16/2016 DONE
plan review failed-sent back to NACFR (Shelley)
1st review completed  9/15/2016 FAIL
DetailsTim Frost
Sprinkler Plan Check9/15/2016 9/15/2016 FAIL
DetailsTim Frost
Miscellaneous action  9/15/2016 DONE
Emailed contractor failed review.
Application received  9/6/2016  
Plan assigned to (Tim)9/6/2016    
DetailsTim Frost
Plan assigned to (Tim)10/7/2016    
DetailsTim Frost
resubmitted plans-ktook to Tom Frost