INSP-Final | 6/11/2020 | 6/12/2020 | 6/12/2020 | A | DONE |
Troy Cobbley
|
|
|
Life safety passed.
Call prior to going Phone #: 2087131061 >> Inspection requested via mobile web by Bill
|
DOC - Permit Finaled | | | 6/12/2020 | | DONE |
|
|
|
per troy c
|
INSP-Conference | 5/29/2020 | 5/29/2020 | 5/29/2020 | P | DONE |
Troy Cobbley
|
|
|
Darren and I went over life safety requirements. Still missing the approved plans.
|
INSP-Final | 3/3/2020 | 3/4/2020 | 3/4/2020 | A | FAIL |
Troy Cobbley
|
|
|
Need city approved plans and small documents on site. The inspection turned into a conference on items needs for a life safety final.
Call for access Phone #: 2082836888 >> Inspection requested via mobile web by Darren
|
Staff review | 6/14/2019 | 6/14/2019 | 6/17/2019 | | PASS |
Mark Scharfen
|
|
|
Completed plan mod 06.17.2019-1 hour total time spent on plan mod.
|
Plan assigned to (Scharfen) | 6/14/2019 | | 6/17/2019 | | PASS |
Mark Scharfen
|
|
|
06.17.2019-Completed review of plan mod. Uploaded rev_fire 06.17.2019.pdf.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/17/2019 | | DONE |
Mark Scharfen
|
|
|
|
Permit Ready to Issue | | | 6/17/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/17/2019 | | DONE |
|
|
|
emailed Shelley that the pkan mod was complete and that there was a 1hr plan mod review time
|
Plan Modification Accepted | | | 6/12/2019 | | DONE |
|
|
|
|
Staff review | 5/24/2019 | 5/24/2019 | 5/24/2019 | | DONE |
Mark Scharfen
|
|
|
plan mod-1 hour.
|
Plan assigned to (Scharfen) | 5/24/2019 | | 5/24/2019 | | DONE |
Mark Scharfen
|
|
|
plan mod from 5/21/19 no changes to fire code report. Complete.
|
Permit Ready to Issue | | | 5/24/2019 | | DONE |
|
|
|
plan mod-1 hr review time
|
CHANGE STATUS TO (ISS) | | | 5/24/2019 | | DONE |
|
|
|
plan mod-1 hr plan review time-emailed Shelley
|
Plan Modification Accepted | | | 5/24/2019 | | DONE |
|
|
|
plan mod in Garden Cities e plan
|
Staff review | 4/16/2019 | 4/16/2019 | 4/16/2019 | | DONE |
Mark Scharfen
|
|
|
IFC Review complete. 2 hours on resubmittal.
|
Plan Modification Accepted | | | 4/16/2019 | | |
|
|
|
plan mod-assigned to MS
|
Plan assigned to (Scharfen) | 4/16/2019 | | 4/16/2019 | | DONE |
Mark Scharfen
|
|
|
IFC Review 04.16.2019.pdf uploaded.
|
Permit Ready to Issue | | | 4/16/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/16/2019 | | DONE |
|
|
|
|
Plan assigned to (Erika) | 4/9/2019 | | 4/16/2019 | | DONE |
Mark Scharfen
|
|
|
|
Staff review | 4/9/2019 | 4/9/2019 | 4/10/2019 | | DONE |
Mark Scharfen
|
|
|
Plan Mod-No review uploaded. 1 hour.
|
Plan Modification Accepted | | | 4/9/2019 | | DONE |
|
|
|
plan mod accepted in GC e plan-changes to pop outs around windows-assigned to EEA
|
Staff review | 9/24/2018 | 9/24/2018 | 9/24/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 9/24/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/24/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/24/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/10/2018 | | DONE |
|
|
|
Resubmittal-was resubmitted in e plan on 9/7/18
|
Plan Modification Accepted | | | 8/3/2018 | | DONE |
|
|
|
plan mod in e plan-submitted a Grade Statement and A7.0 Struc Notes, VP03 const plans ST1, VP03 const plans ST2, VP03 water plans ST1, VP03 water plans ST2
|
Staff review | 6/25/2018 | 6/25/2018 | 6/29/2018 | | PASS |
Tim Frost
|
|
|
plan mod resubmitted through e plan
Not really sure why it was routed to fire. There was only some electrical changes.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/29/2018 | | DONE |
|
|
|
|
Staff review | 6/8/2018 | 6/8/2018 | 6/8/2018 | | PASS |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/8/2018 | | DONE |
|
|
|
|
Issue and Courier | | | 6/8/2018 | | DONE |
|
|
|
emailed Shelley
|
Sprinkler Plan Check | 6/8/2018 | | 6/8/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/8/2018 | | DONE |
|
|
|
|
Telephone call | | | 2/15/2018 | | DONE |
Scott Arellano
|
|
|
Spoke with Rick George (RDP). The provided fire flow is 1,500 gpm which remains below the required minimum 2,750 gpm needed for the proposed building. Rick indicated that fully fire sprinklering the building will need to occur to resolve this issue. He will resubmit the architectual cover sheet indicating the building to be fully fire sprinklered in accordance with NFPA 13. Rick will submit this revised plan to Garden City Development Services for distribution to the Building Official and NACFR.
|
Plan assigned to (Scott) | 2/6/2018 | | 2/9/2018 | | FAIL |
Scott Arellano
|
|
|
Emailed architect plan review report. Attached report to e-case and permit case. report also went to Shelley @ NACFR
|
Plan resubmittals received | | | 2/6/2018 | | DONE |
|
|
|
resubmittals/plan mod received-attached revised permit-assigned to Scott A
|
Application received | | | 10/19/2016 | | |
|
|
|
|
Plan assigned to (Katie) | 10/19/2016 | | 10/19/2016 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
1st review completed | | | 10/19/2016 | | FAIL |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/19/2016 | | |
|
|
|
|
Plan assigned to (Tim) | 9/10/2018 | | | | |
Tim Frost
|
|
|
|
Plan assigned to (Adele) | 6/25/2018 | | | | |
Adele J Schaffeld-Griffin
|
|
|
plan mod submitted through e plan
|