INSP-Final | 8/24/2017 | 8/25/2017 | 8/25/2017 | A | DONE |
Troy Cobbley
|
|
|
permit finaled
|
DOC - Permit Finaled | | | 8/25/2017 | | DONE |
|
|
|
Passed final per Troy
|
Sprinkler Plan Check | 8/17/2017 | | 8/17/2017 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/17/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/17/2017 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 8/17/2017 | | DONE |
|
|
|
as per Tim Frost-plan mod as built- no fees due-sent email to Shelley and put plans in the inner office mail
|
Plan Modification Accepted | | | 8/14/2017 | | DONE |
|
|
|
received as built plan mod-received 4 app's, 4 sheets FP-2 & 1 cover sheet ffrom NACFR-put in cubby for Tim Frost
|
INSP-Final | 8/9/2017 | 8/11/2017 | 8/11/2017 | A | FAIL |
Troy Cobbley
|
|
|
Repair the retaining straps, provide the calc sticker and provide the updated approved drawings for the earthquake bracing locations
|
INSP-Sprinkler Rough-in/Hydro | 8/3/2017 | 8/4/2017 | 8/4/2017 | A | PART |
Troy Cobbley
|
|
|
Inspection turned into a conference. Hydro test has already been performed. Earth quake bracing is not installed in the approved locations. It will need to be installed as approved or calculations resubmitted for the new locations. Retaining straps are still not installed correctly. Need cap on FDC. Need sticker on bell. Need service tag on riser. Need data sheet on the test valve that it has the correct orfice for the inspector test. Need forward flush done. And ultimately need the fire alarm interconnections verified.
|
Plan Modification Accepted | | | 7/18/2017 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/18/2017 | | 7/18/2017 | | PASS |
Tim Frost
|
|
|
Modified Canopy
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/18/2017 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/18/2017 | | DONE |
|
|
|
emailed Shelley that the permit was in the inner office mail
|
INSP-Sprinkler Rough-in/Hydro | 7/17/2017 | 7/17/2017 | 7/17/2017 | A | PART |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping complete. Sway bracing installation does not match what is on the city approved drawings, sway bracing will need to be repaired, numerous retaining straps throughout space are not installed correctly (straps found need to be bent around truss to retain beam clamp) As-builts will need to be completed and submitted for pipe that was installed around HVAC penetrations through deck.
|
Plan Modification Accepted | | | 7/17/2017 | | DONE |
|
|
|
Plan Mod received 1 sheet of the app, 4 cover sheets & 4 sheets of FP2-put in cubby for Tim Frost
|
Sprinkler Plan Check | 6/6/2017 | | 6/6/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/6/2017 | | DONE |
|
|
|
|
Issue and Courier | | | 6/6/2017 | | DONE |
|
|
|
emailed Shelley that plans were in the inner office mail
|
Plan resubmittals received | | | 6/5/2017 | | DONE |
|
|
|
resubmittal recieved 1permit app & calc summary, 4 sets of calcs & parts info & 1 set of sheets FP1 and FP2-put in cubby for Tim F
|
Plan resubmittals received | | | 6/1/2017 | | DONE |
|
|
|
resubmittal recieved 4 sets of sheets FP1 & FP2, 3 of each permit app, calcs summary, seismic bracing calcs,equip-put in cubby for Tim Frost
|
Miscellaneous action | | | 5/30/2017 | | DONE |
|
|
|
plans fialed so sent plans back to Shelley threw inner office mail
|
Plan resubmittals received | | | 5/25/2017 | | DONE |
|
|
|
resubmittlas received 4 sets of sheets FP1 & FP2 and 3 sets of the permit app, calc summary, hydraulic calcs and the fire protection products-put in cubby for Tim Frost
|
Sprinkler Plan Check | 5/18/2017 | | 5/18/2017 | | FAIL |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 5/18/2017 | | 5/18/2017 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 5/18/2017 | | DONE |
|
|
|
Sent contractor failed review.
|
Miscellaneous action | | | 5/18/2017 | | DONE |
|
|
|
emailed Shelley that plan review failed-Tim Frost emailed customers-plans are at Candy's desk-Shelley is on vacation and we'll send to her next week
|
Plan resubmittals received | | | 5/17/2017 | | DONE |
|
|
|
resubfmittals received 3 sets of the apps, calcs & 4 sets of sheets FP1 &FP2-put in cubby for Tim F
|
1st review completed | | | 4/3/2017 | | FAIL |
|
|
|
|
Sprinkler Plan Check | 4/3/2017 | | 4/3/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 4/3/2017 | | DONE |
|
|
|
Emailed contractor review.
|
Plan assigned to (Tim) | 4/3/2017 | | 4/3/2017 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 4/3/2017 | | DONE |
|
|
|
permit was denied so put in inner office mail and emailed Shelley that it was on it's way back to her
|
Application received | | | 3/30/2017 | | DONE |
|
|
|
|
Meeting | | | 3/30/2017 | | DONE |
|
|
|
sent email to Shelley
|
Plan assigned to (Tim) | 7/17/2017 | | | | |
Tim Frost
|
|
|
Plan Mod
|
Plan assigned to (Tim) | 8/14/2017 | | | | |
Tim Frost
|
|
|
|