INSP-Final | 9/25/2017 | 9/26/2017 | 9/26/2017 | A | DONE |
Troy Cobbley
|
|
|
Permit finaled
|
DOC - Permit Finaled | | | 9/26/2017 | | DONE |
Rita DeYoung
|
|
|
Per Troy permit finaled
|
INSP-Final | 9/22/2017 | 9/25/2017 | 9/25/2017 | A | CANC |
Troy Cobbley
|
|
|
After ten am Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Sprinkler Rough-in | 8/22/2017 | 8/23/2017 | 8/23/2017 | A | PASS |
Troy Cobbley
|
|
|
Tie in piping is approved for cover. The fitting is going to repair the insulation/tenting in the new area. Per the general contractor the insulating contractor will tent the tie-ins. He will provide documentation to me when that work is done.
|
INSP-Sprinkler Rough-in/Hydro | 8/18/2017 | 8/22/2017 | 8/22/2017 | A | PASS |
Troy Cobbley
|
|
|
24 hour are test passed for the new addition
|
INSP-Sprinkler Rough-in/Hydro | 8/18/2017 | 8/21/2017 | 8/21/2017 | A | PART |
Troy Cobbley
|
|
|
24 hour air test started at 7:15 with 84psi on the guage.
|
INSP-Sprinkler Rough-in | 8/18/2017 | 8/18/2017 | 8/18/2017 | P | PART |
Troy Cobbley
|
|
|
Tenting passed and wet system piping rough-in passed. Piping can be covered as marked on the city approved plans. Will need another cover inspection once the two tie -ins are complete. Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in/Hydro | 8/14/2017 | 8/14/2017 | 8/14/2017 | P | PART |
Jim Page
|
|
|
Hydrostatic test complete for both wet and dry systems in area of work. Rough to cover inspection for dry systen complete, dry system is approved for cover. Rough in inspection complete for wet system area of work, wet system piping cannot be covered until tenting of wet system overhead fire sprinkler piping is complete and inspected.
|
1st review completed | | | 6/9/2017 | | PASS |
|
|
|
|
Sprinkler Plan Check | 6/9/2017 | | 6/9/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/9/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/9/2017 | | DONE |
|
|
|
|
Issue and Courier | | | 6/9/2017 | | DONE |
|
|
|
emailed Shelley it was in the inner office mail for Monday
|
Application received | | | 6/8/2017 | | |
|
|
|
|
Plan assigned to (Tim) | 6/8/2017 | | | | |
Tim Frost
|
|
|
|