INSP-Final | 7/19/2017 | 7/19/2017 | 7/19/2017 | P | PASS |
Troy Cobbley
|
|
|
Life Safety passed.
|
DOC - Permit Finaled | | | 7/19/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/10/2017 | | DONE |
|
|
|
|
Issue and Courier | | | 7/10/2017 | | DONE |
|
|
|
email from Scott stating that the permit was ready to be issued:
Hi Candy,
This NAF permit case can be changed to issued. The plan review correction item was addressed last week on the same the original review was completed (July5th). No additional fee necessary.
Scott Arellano
Fire Protection Systems Supv
Planning and Development Services
Office: ###-####
sarellano@cityofboise.org
Making Boise the most livable city in the country.
|
Plan assigned to (Scott) | 6/29/2017 | | 7/5/2017 | | FAIL |
Scott Arellano
|
|
|
Emailed plan review report to applicant and Building Official. Attached report to case.
|
1st review completed | | | 7/5/2017 | | FAIL |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/5/2017 | | |
|
|
|
|
Telephone call | | | 7/5/2017 | | DONE |
Scott Arellano
|
|
|
Communicated via email with Brigette Nelson (applicant). Applicant indicated that no wood working would be taking place in the facility and other tools used for making jewelry etc would have means for local dust collection. Provided additional information fire extinguishers and exit signage.
|
Plan resubmittals received | | | 7/5/2017 | | DONE |
|
|
|
Additional information received.
|
Plan assigned to (Scott) | 7/5/2017 | | 7/5/2017 | | PASS |
Scott Arellano
|
|
|
Attached revised plan review report to Building Official and attached to case and eplan.
|
Application received | | | 6/29/2017 | | |
|
|
|
SJA - Can be changed to Issued. 7/10/17
|