INSP-Final | 1/11/2018 | 1/12/2018 | 1/12/2018 | P | PASS |
Scott Arellano
|
|
|
Follow up inspection passed.
|
DOC - Permit Finaled | | | 1/12/2018 | | DONE |
|
|
|
Per Scott A
|
INSP-Final | 1/10/2018 | 1/11/2018 | 1/11/2018 | P | FAIL |
Troy Cobbley
|
|
|
Need a plug for the end of the sample tube and the duct smoke detector repaired. Per Troy James and Lee it appears the duct smoke detector is not even required in a make up air unit so there is the option of removing the equipment and voiding the permit.
Tech-John Howard Phone #: ###-#### Inspection requested via web by John Siewert
|
1st review completed | | | 12/19/2017 | | PASS |
|
|
|
|
Sprinkler Plan Check | 12/19/2017 | | 12/19/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 12/19/2017 | | DONE |
|
|
|
Plans approved with review comments.
|
Permit Ready to Issue | | | 12/19/2017 | | DONE |
|
|
|
|
Issue and Courier | | | 12/19/2017 | | DONE |
|
|
|
|
Application received | | | 12/15/2017 | | |
|
|
|
|
Plan assigned to (Lee) | 12/15/2017 | | | | |
Lee G Meredith
|
|
|
|