INSP-Final | 4/18/2018 | 4/19/2018 | 4/19/2018 | A | DONE |
Troy Cobbley
|
|
|
Life safety passed
>> Inspection requested via mobile web by Ian
|
DOC - Permit Finaled | | | 4/19/2018 | | DONE |
Troy Cobbley
|
|
|
as per Troy C-doc final-won't let him do it in the field
|
Permit Ready to Issue | | | 4/13/2018 | | DONE |
|
|
|
|
Issue and Courier | | | 4/13/2018 | | DONE |
|
|
|
emailed Shelley
|
Staff review | 4/12/2018 | 4/12/2018 | 4/12/2018 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Plan assigned to (Adele) | 4/12/2018 | | 4/12/2018 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/12/2018 | | DONE |
|
|
|
|
Plan assigned to (Erika) | 3/28/2018 | | 4/12/2018 | | DONE |
Erika Akin
|
|
|
Adele Completed review
|
Staff review | 3/30/2018 | 3/30/2018 | 3/30/2018 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Building department needs to set occupant load prior to fire review
|
Application received | | | 3/28/2018 | | |
|
|
|
|
Miscellaneous action | | | 3/28/2018 | | DONE |
|
|
|
emailed Shelley, Adele & Erika
|