INSP-Final | 9/20/2018 | 9/21/2018 | 9/21/2018 | P | DONE |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
DOC - Permit Finaled | | | 9/21/2018 | | DONE |
|
|
|
Per troy james
|
INSP-Supply line flush | 8/29/2018 | 8/30/2018 | 8/30/2018 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Supply line flush | 8/29/2018 | 8/29/2018 | 8/29/2018 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Matthew Lewis Inspection cancelled from web by: Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 8/8/2018 | 8/9/2018 | 8/9/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for unerground supply witnessed, no pressure loss observed at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 7/10/2018 | 7/11/2018 | 7/11/2018 | A | FAIL |
Troy Cobbley
|
|
|
underground hydro
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 6/18/2018 | 6/19/2018 | 6/19/2018 | A | PASS |
Troy Cobbley
|
|
|
The remaining underground piping is ok for cover.
|
INSP-Sprinkler Rough-in | 4/11/2018 | 4/11/2018 | 4/11/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for IBR (In Building Riser) and stub out from the footing complete, IBR and stub out approved for cover, remaining underground to be installed at a later date.
|
Sprinkler Plan Check | 4/11/2018 | | 4/11/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/11/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/11/2018 | | DONE |
|
|
|
Tim didn't sign off on the assign to but said it's ready
|
Issue and Courier | | | 4/11/2018 | | DONE |
|
|
|
emailed Shelley that the permit was in theinner office mail heading her way
|
Application received | | | 4/5/2018 | | |
|
|
|
|
Plan assigned to (Tim) | 4/5/2018 | | | | |
Tim Frost
|
|
|
|