INSP-Final | 8/20/2019 | 8/20/2019 | 8/20/2019 | A | PART |
Jim Page
|
|
|
Final underground supply inspection complete.
|
INSP-Supply line flush | 8/19/2019 | 8/20/2019 | 8/20/2019 | A | DONE |
Jim Page
|
|
|
Undergorund main line flush complete.
Please contact Troy Nelson, for a time frame, so we can coordinate with Garden City Water Dept. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
DOC - Permit Finaled | | | 8/20/2019 | | DONE |
|
|
|
per Jim Page
|
INSP-Sprinkler Rough-in/Hydro | 8/5/2019 | 8/5/2019 | 8/5/2019 | P | PASS |
Troy Cobbley
|
|
|
The underground supply line hydro test was witnessed with no pressure loss.
Please call Troy Nelson for inspection time. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in | 11/15/2018 | 11/15/2018 | 11/15/2018 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping rough-in passed. Piping can be covered.
Troy, will call when completed this morning. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
Staff review | 11/1/2018 | 11/1/2018 | 11/8/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 11/1/2018 | | 11/8/2018 | | DONE |
Tim Frost
|
|
|
per Tim Frost passed inspection
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/8/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 11/8/2018 | | DONE |
|
|
|
|
Issue and Courier | | | 11/8/2018 | | DONE |
|
|
|
|
Miscellaneous action | | | 11/8/2018 | | DONE |
|
|
|
emailed Shelley taht the plan review passed review-as per Shelley customer will come pick the permit up at the City-plans are at Candy's desk
|
Miscellaneous action | | | 11/1/2018 | | DONE |
|
|
|
emailed Shelley permit # and app
|
Application received | | | 11/1/2018 | | |
|
|
|
|