INSP-Final | 4/26/2019 | 4/30/2019 | 4/30/2019 | A | PASS |
Mark Scharfen
|
|
|
Passed sprinkler final. Performed foward flush. Flow activated in 30 seconds.
We would like to perform this inspection in conjunction with fire alarm testing. Please call Rick with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
DOC - Permit Finaled | | | 4/30/2019 | | DONE |
Mark Scharfen
|
|
|
as per Mark Scharfen-doc final permit-final passed but they can't doc final in the field
|
INSP-Sprinkler Rough-in | 2/28/2019 | 2/28/2019 | 2/28/2019 | P | CANC |
Troy Cobbley
|
|
|
Wrong permit number called in.
|
INSP-Supply line flush | 1/30/2019 | 1/31/2019 | 1/31/2019 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 1/17/2019 | 1/18/2019 | 1/18/2019 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro test witnessed
|
INSP-Sprinkler Rough-in | 1/11/2019 | 1/14/2019 | 1/14/2019 | A | PASS |
Troy Cobbley
|
|
|
The underground supply piping is ok for cover.
This is cover inspection for Underground. Please call Troy Nelson with Questions. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
Staff review | 12/11/2018 | 12/11/2018 | 12/17/2018 | | DEFR |
Erika Akin
|
|
|
|
Sprinkler Plan Check | 12/17/2018 | | 12/17/2018 | | DONE |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/17/2018 | | |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 12/17/2018 | | 12/17/2018 | | DONE |
Mark Stumbaugh
|
|
|
Mark signed off on the staff assigned to
|
Permit Ready to Issue | | | 12/17/2018 | | DONE |
|
|
|
|
Issue and Courier | | | 12/17/2018 | | DONE |
|
|
|
emailed Shelley permit is ready and that it's in the inner office mail
|
Miscellaneous action | | | 12/11/2018 | | DONE |
|
|
|
emailed Shelley the dpermit app and NAF #
|
Application received | | | 12/11/2018 | | |
|
|
|
|