INSP-Final | 4/4/2019 | 4/4/2019 | 4/4/2019 | P | DONE |
Troy Cobbley
|
|
|
Permit finaled
Phone #: 2086157641 >> Inspection requested via mobile web by Richard Johnson
|
DOC - Permit Finaled | | | 4/4/2019 | | DONE |
|
|
|
per troy
|
INSP-Final | 3/27/2019 | 3/29/2019 | 3/29/2019 | P | FAIL |
Troy Cobbley
|
|
|
Need correct testing for the piping as discussed, need barrier between fryer and char broiler, need power under the hood to shut off as discussed.
Call prior to going Phone #: 2086157641 >> Inspection requested via mobile web by Richard
|
INSP-Final | 3/27/2019 | 3/29/2019 | 3/27/2019 | P | CANC |
Troy Cobbley
|
|
|
Phone #: 2082584094 >> Inspection requested via mobile web by Britney Inspection cancelled via mobile web on Wednesday, March 27, 2019.
|
Staff review | 3/12/2019 | 3/12/2019 | 3/12/2019 | | PASS |
Mark Stumbaugh
|
|
|
4th resubmittal
|
Plan resubmittals received | | | 3/12/2019 | | DONE |
|
|
|
4th resubmittal-staff review to MAS 1 hr review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/12/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 3/12/2019 | | DONE |
|
|
|
|
Issue and Courier | | | 3/12/2019 | | DONE |
|
|
|
emailed Shelley that it was in the inner office mail coming her way
|
Staff review | 3/7/2019 | 3/7/2019 | 3/7/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 3/7/2019 | | DONE |
|
|
|
3rd resubmittal-took to MAS
|
Miscellaneous action | | | 3/4/2019 | | DONE |
|
|
|
sent email from Mark Stumbaugh to Shelley
|
Staff review | 3/1/2019 | 3/1/2019 | 3/1/2019 | | FAIL |
Mark Stumbaugh
|
|
|
1 hr plan review fee
|
Plan assigned to (Stumbaugh) | 3/1/2019 | | 3/1/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 3/1/2019 | | DONE |
|
|
|
Resubmittals recieved 3 sets of corrections-took to Mark Stumaugh
|
Staff review | 2/25/2019 | 2/25/2019 | 2/26/2019 | | FAIL |
Mark Stumbaugh
|
|
|
Corrections needed
|
Plan assigned to (Stumbaugh) | 2/25/2019 | | 2/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
Review time 1 hr
|
Miscellaneous action | | | 2/26/2019 | | DONE |
|
|
|
emailed Shelley the failed email with the plan review time on it
|
Miscellaneous action | | | 2/25/2019 | | DONE |
|
|
|
emailed Shelley the NAF #
|
Application received | | | 2/25/2019 | | |
|
|
|
|