INSP-Final | 6/5/2019 | 6/6/2019 | 6/6/2019 | A | DONE |
Troy Cobbley
|
|
|
Permit finaled. Suppression system function witnessed.
Call prior to going Phone #: 2086317804 >> Inspection requested via mobile web by Nate
|
DOC - Permit Finaled | | | 6/6/2019 | | DONE |
Troy Cobbley
|
|
|
as per Troy C. doc final-final insp passed
|
INSP-Final | 5/1/2019 | 5/2/2019 | 5/2/2019 | A | FAIL |
Troy Cobbley
|
|
|
Plan mods are needed for one hood due to changed nozzles numbers and one additional nozzle at the grill. All nozzles/piping needs braced and tightened so it does not spin in the fittings. Lights need to be repaired so shut off upon activation of the suppression system can be verified.
Call prior to going Phone #: 2086319935 >> Inspection requested via mobile web by Nate
|
Staff review | 4/5/2019 | 4/5/2019 | 4/8/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/5/2019 | | 4/8/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 4/8/2019 | | DONE |
|
|
|
|
Issue and Courier | | | 4/8/2019 | | DONE |
|
|
|
emailed Shelley that the permit is issued and in the inner office mail
|
Plan resubmittals received | | | 4/5/2019 | | DONE |
|
|
|
resubmittals received-assigned to MAS
|
Staff review | 3/21/2019 | 3/21/2019 | 3/25/2019 | | FAIL |
Mark Stumbaugh
|
|
|
1 hr plan review time
|
Miscellaneous action | | | 3/25/2019 | | DONE |
|
|
|
emailed Shelley that it failed and that there was a 1 hr review time
|
Plan resubmittals received | | | 3/21/2019 | | DONE |
|
|
|
resubmittals recieved-assigned and took to MAS
|
Staff review | 3/19/2019 | 3/19/2019 | 3/19/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 3/19/2019 | | 3/19/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Miscellaneous action | | | 3/19/2019 | | DONE |
|
|
|
emailed Shelley the app and NAF #
|
Miscellaneous action | | | 3/19/2019 | | DONE |
|
|
|
emailed Shelley that the plan review failed
|
Application received | | | 3/19/2019 | | |
|
|
|
|