INSP-Final | 5/31/2019 | 6/3/2019 | 6/3/2019 | A | DONE |
Troy Cobbley
|
|
|
Permit finaled
Contact is Raul Phone #: ###-#### Inspection requested via web by Chris Green
|
DOC - Permit Finaled | | | 6/3/2019 | | DONE |
|
|
|
per Troy Cobbley doc final
|
INSP-Final | 5/28/2019 | 5/29/2019 | 5/29/2019 | A | CANC |
Troy Cobbley
|
|
|
Not ready for final. Need ceiling tile installed.
Raul is the Contact. Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Sprinkler Rough-in | 5/28/2019 | 5/29/2019 | 5/29/2019 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping is ok for cover. Inspection was by Mark Stumbaugh.
Raul is the Contact. Phone #: ###-#### Inspection requested via web by Chris Green
|
Staff review | 5/10/2019 | 5/10/2019 | 5/13/2019 | | PASS |
Mark Stumbaugh
|
|
|
Review Time 1hr
|
Plan assigned to (Stumbaugh) | 5/10/2019 | | 5/13/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 5/13/2019 | | DONE |
|
|
|
|
Issue and Courier | | | 5/13/2019 | | DONE |
|
|
|
emailed Shelley taht it was in the inner office to come back to her
|
Miscellaneous action | | | 5/10/2019 | | DONE |
|
|
|
emailed Shelley the permit #
|
Application received | | | 5/10/2019 | | |
|
|
|
|