INSP-Final | 12/6/2019 | 12/9/2019 | 12/9/2019 | A | PASS |
Troy Cobbley
|
|
|
***PASS Hydro papers uploaded to tidemark*MAS*** Gabe is the contact. Thanks for all you do! Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
DOC - Permit Finaled | | | 12/9/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 12/5/2019 | 12/6/2019 | 12/6/2019 | A | PASS |
Troy Cobbley
|
|
|
**PASS* Hydro passed. Heads that were blocked byfaux beams have been relocated.*MAS***
Gabe is the contact.Thanks for all you do! Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 11/25/2019 | 11/25/2019 | 11/25/2019 | P | FAIL |
Troy Cobbley
|
|
|
** Fail - Heads in great room need to be relocated due to newly installed faux beams* MAS**
Gabe is the field contact. Thanks for all you do! Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 8/20/2019 | 8/21/2019 | 8/21/2019 | A | PASS |
Troy Cobbley
|
|
|
*** Pipe tenting passed. Ok to cover. Good work Gabe**MAS** Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 8/19/2019 | 8/20/2019 | 8/20/2019 | A | FAIL |
Troy Cobbley
|
|
|
***Piping in attic leading up to upper ceiling heads in family room, and entryway still need tenting/insulation corrected*** Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 8/14/2019 | 8/15/2019 | 8/15/2019 | P | FAIL |
Troy Cobbley
|
|
|
Tenting still needs modified in the bedroom with the soffit, insulation needs to be added at both sides of the two drops in this room to keep blow-in insulation out and heat in. Also the two 1" pipe risers that supply piping in the living room vaulted ceiling have been installed on the outside of the plywood. They have been insulated/tented vertically but when the owner insulates the wall it will effectively block off the transfer of heat. The pipe should be relocated to the inside of the wall and insulation placed behind the piping.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 8/13/2019 | 8/14/2019 | 8/14/2019 | A | FAIL |
Troy Cobbley
|
|
|
*Areas that need additional tenting marked in red on approved drawings. Hydro failed dropped from 210 to 182 psi. Underground piping not installed yet.**MAS**
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
Staff review | 8/7/2019 | 8/7/2019 | 8/7/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 8/7/2019 | | 8/7/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Miscellaneous action | | | 8/7/2019 | | DONE |
|
|
|
emailed Shelley the app and NAF permit #
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/7/2019 | | DONE |
Mark Stumbaugh
|
|
|
Review Time 1hr
|
Permit Ready to Issue | | | 8/7/2019 | | DONE |
|
|
|
|
Issue and Courier | | | 8/7/2019 | | DONE |
|
|
|
emailed Shelley that the permit is in the inner office mail to come back to her
|
Application received | | | 8/7/2019 | | |
|
|
|
|