INSP-Final | 4/23/2020 | 4/24/2020 | 4/24/2020 | A | DONE |
Troy Cobbley
|
|
|
Permit finaled. Call Alicia when heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
DOC - Permit Finaled | | | 4/24/2020 | | DONE |
|
|
|
per troy c
|
INSP-Sprinkler Rough-in/Hydro | 9/15/2019 | 9/16/2019 | 9/16/2019 | P | PASS |
Troy Cobbley
|
|
|
**Hydro and Tenting passed* MAS**
Hydro and tenting needed, rough passed last week. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 9/12/2019 | 9/13/2019 | 9/13/2019 | P | PART |
Jim Page
|
|
|
Hydro was not ready, rough in inspection complete, piping between conditioned spaces approved for cover, not all tenting in place at time of inspection, cover is not approved where tenting is required.
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 9/11/2019 | 9/12/2019 | 9/12/2019 | P | FAIL |
Jim Page
|
|
|
Sprinkler head/heads at top of stairs do not extend past wall as shown on approved drawings.
Call Anthony before heading out Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Staff review | 9/11/2019 | 9/11/2019 | 9/11/2019 | | PASS |
Mark Stumbaugh
|
|
|
plan mod
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/11/2019 | | DONE |
Mark Stumbaugh
|
|
|
Plan Mod Fee $150.00
|
Permit Ready to Issue | | | 9/11/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/11/2019 | | DONE |
|
|
|
plan mod-emailed Shelley taht this was in the inner office mail heading back her way
|
Plan Modification Accepted | | | 9/11/2019 | | DONE |
|
|
|
plan mod-changing heads in closet-assigned and took to Mark Stumbaugh
|
Plan assigned to (Stumbaugh) | 9/11/2019 | | 9/11/2019 | | DONE |
Mark Stumbaugh
|
|
|
plan mod
|
INSP-Sprinkler Rough-in/Hydro | 9/4/2019 | 9/5/2019 | 9/5/2019 | P | PART |
Troy Cobbley
|
|
|
Plan mods need to be submitted showing the actual pipe routing, fittings and additional supply to second floor. Need tenting inspection when complete. Rough-in appears ok, just need the plans to match. Also the short piece at the top of the riser has been installed 3/4" instead of 1". No piping to be covered yet.
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Permit Ready to Issue | | | 8/27/2019 | | DONE |
|
|
|
|
Issue and Courier | | | 8/27/2019 | | DONE |
|
|
|
emailed Shelley that permit is issued-called Carly to let know they coulld come pick up permits (they need to pick up all 12)
|
Staff review | 8/26/2019 | 8/26/2019 | 8/26/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 8/26/2019 | | 8/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Miscellaneous action | | | 8/26/2019 | | DONE |
|
|
|
Emailed Shelley the NAF # and app-Carly with Thorp brought to us because Shelley is lout this week
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
Review Time 1hr
|
Application received | | | 8/26/2019 | | |
|
|
|
|