INSP-Final | 9/18/2019 | 9/19/2019 | 9/19/2019 | P | DONE |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
DOC - Permit Finaled | | | 9/19/2019 | | DONE |
|
|
|
Per Jim Page and passing final inspection
|
INSP-Sprinkler Rough-in | 9/5/2019 | 9/5/2019 | 9/5/2019 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping is ok for cover.
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Staff review | 8/30/2019 | 8/30/2019 | 8/30/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Miscellaneous action | | | 8/30/2019 | | DONE |
|
|
|
emailed Shelley NAF permit number
|
Plan assigned to (Stumbaugh) | 8/30/2019 | | 8/30/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/30/2019 | | DONE |
Mark Stumbaugh
|
|
|
Review Time 1hr
|
Permit Ready to Issue | | | 8/30/2019 | | DONE |
|
|
|
emailed Shelly to inform her the permit is ready and what fee was due
|
Issue and Courier | | | 8/30/2019 | | DONE |
|
|
|
Called applicant
|
Application received | | | 8/30/2019 | | |
|
|
|
|