INSP-Final | 3/16/2020 | 3/16/2020 | 3/16/2020 | P | DONE |
Troy Cobbley
|
|
|
Kc Strykowski, Technician Phone #: ###-#### Inspection requested via web by John Siewert
|
DOC - Permit Finaled | | | 3/16/2020 | | DONE |
|
|
|
Per Troy Cobbley
|
INSP-Final | 3/10/2020 | 3/13/2020 | 3/13/2020 | A | PART |
Troy Cobbley
|
|
|
Kc Strykowski, Tech Phone #: ###-#### >> Inspection requested via web by John Siewert
Still to test: All smoke and heat detectors, all notification in ada units. Everything else has been tested.
|
INSP-Final | 1/28/2020 | 1/30/2020 | 1/30/2020 | P | FAIL |
Greg Ruxton
|
|
|
Inspection stopped based on noted deficiencies. Exterior pull stations not listed for outdoor use, plans on site did not include Rm 111, a Knox Box was not installed, a copy of supervising station signal reports was not complete.
Contractor to change exterior pull stations, install Knox Box after consulting with Garden City Fire Department, provide updated map reflecting floor plan and all device locations and test 100 percent of devices and provide copy of supervising station reports.
John Howard, Technician Phone #: ###-#### Inspection requested via web by John Siewert
|
Permit Ready to Issue | | | 1/21/2020 | | DONE |
|
|
|
As built passed
|
CHANGE STATUS TO (ISS) | | | 1/21/2020 | | DONE |
|
|
|
as built passed
|
1st review completed | | | 1/17/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 1/17/2020 | | 1/17/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 1/17/2020 | | DONE |
|
|
|
Taken to Tiffany for processing.
|
Plan assigned to (Lee) | 1/16/2020 | | 1/17/2020 | | DONE |
Lee G Meredith
|
|
|
as builts
|
Plan resubmittals received | | | 1/16/2020 | | DONE |
|
|
|
as built plans turned in
|
Staff review | 11/12/2019 | 11/12/2019 | 11/13/2019 | | DONE |
Lee G Meredith
|
|
|
|
Plan assigned to (Lee) | 11/12/2019 | | 11/13/2019 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 11/13/2019 | | DONE |
|
|
|
|
Alarm Plan Check | 11/13/2019 | | 11/13/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 11/13/2019 | | DONE |
|
|
|
Passed with review comments.
|
Permit Ready to Issue | | | 11/13/2019 | | DONE |
|
|
|
|
Issue and Courier | | | 11/13/2019 | | DONE |
|
|
|
Emailed Shelley
|
Miscellaneous action | | | 11/12/2019 | | DONE |
|
|
|
emailed Shelley the NAF number
|
Application received | | | 11/12/2019 | | |
|
|
|
|