Telephone call | | | 5/22/2001 | | DONE |
Kim Harrison
|
|
|
|
(F) Reprint permit | | | 5/22/2001 | | DONE |
|
|
|
|
(F) Reprint permit | | | 5/22/2001 | | DONE |
|
|
|
|
Final | 2/28/2001 | 3/1/2001 | 3/1/2001 | A | PASS |
Bill VanDegrift
|
|
|
Scheduled by Inspector: 330 On 2/28/2001 9:29:58 AM rp on pressure washer for final, final ok 3/1/2001 9:01:24 AM
|
DOC - Permit Finaled | 3/1/2001 | 3/1/2001 | 3/1/2001 | A | PASS |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 3/1/2001 9:15:11 AM
|
Final | 2/27/2001 | 2/28/2001 | 2/28/2001 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 02/27/2001 at 16:09:30. Contact: ###-####.
|
Final | 1/29/2001 | 1/30/2001 | 1/30/2001 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 01/29/2001 at 15:32:29. Contact: ###-####. test all bfp's, install all fixtures and equipment coffee makers, steam equipment, shop equipment, install solid covers on interceptor, install dip tubes on interceptor, install drain on water heater pan, flash all roof penitrations 1/30/2001 10:37:41 AM
|
Roof Drains | 12/27/2000 | 12/28/2000 | 12/27/2000 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 12/27/2000 at 11:00:04. Contact: ###-####. 6" main roofdrain ok 12/27/2000 2:26:00 PM
|
Storm Drains | 11/8/2000 | 11/8/2000 | 11/8/2000 | P | FAIL |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 11/8/2000 they seem to have the down stream baffles sealed ok but when they pulled the lids to seal then they exposed the relocated upstream baffles thar have a 1/2" gap at the wall joint that needs to be grouted
|
Storm Drains | 11/6/2000 | 11/6/2000 | 11/6/2000 | P | FAIL |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 11/6/2000 interceptor test failed
|
Other | 11/2/2000 | 11/2/2000 | 11/2/2000 | P | FAIL |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 11/2/2000 drainage from hangar ok interceptor test failed
|
Plumbing Rough-in | 10/31/2000 | 11/1/2000 | 11/1/2000 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 10/31/2000 at 14:55:29. Contact: ###-####. shop area walls ok to cover 11/1/2000 9:36:21 AM
|
Groundwork | 10/20/2000 | 10/20/2000 | 10/20/2000 | A | PART |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 10/20/2000 track drains east side
|
Groundwork | 10/18/2000 | 10/19/2000 | 10/19/2000 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 10/18/2000 at 11:45:35. Contact: ###-####. 18" fire water drain ok needs test 10/19/2000 11:35:37 AM
|
Groundwork | 10/18/2000 | 10/19/2000 | 10/19/2000 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 10/18/2000 at 11:45:35. Contact: ###-####. 18" fire water drain ok needs test 10/19/2000 11:35:37 AM
|
Groundwork | 10/18/2000 | 10/18/2000 | 10/18/2000 | P | PART |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 10/18/2000 snow melt
|
Water and/or Sewer | 10/16/2000 | 10/16/2000 | 10/16/2000 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 10/16/2000 at 10:11:33. Contact: ###-####. partial ri ok east restroom and steamroom 10/16/2000 3:44:55 PM
|
Roof Drains | 9/25/2000 | 9/25/2000 | 9/25/2000 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 09/25/2000 at 08:32:50. Contact: ###-####. west side 9/25/2000 3:58:56 PM
|
Water and/or Sewer | 9/25/2000 | 9/25/2000 | 9/25/2000 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 09/25/2000 at 08:33:17. Contact: ###-####. partial ri west side w&v water and roof drains 9/25/2000 3:58:41 PM
|
Groundwork | 8/30/2000 | 8/31/2000 | 8/31/2000 | A | PASS |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 08/30/2000 at 13:38:57. Contact: ###-####.
|
Groundwork | 8/29/2000 | 8/30/2000 | 8/30/2000 | A | FAIL |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 08/29/2000 at 14:46:12. Contact: ###-####.backgrade on 3" around corner to main blding. 8/30/2000 2:19:16 PM
|
Groundwork | 8/14/2000 | 8/14/2000 | 8/14/2000 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 08/14/2000 at 08:09:43. Contact: ###-####. 3" and 2" wastes east end 8/14/2000 10:14:45 AM
|
Groundwork | 8/10/2000 | 8/10/2000 | 8/10/2000 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 08/10/2000 at 11:15:48. Contact: ###-####. 2-3" wastes east end 8/10/2000 2:27:00 PM
|
Groundwork | 8/4/2000 | 8/4/2000 | 8/4/2000 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 08/04/2000 at 08:26:48. Contact: ###-####.
|
Groundwork | 7/31/2000 | 8/1/2000 | 8/1/2000 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 07/31/2000 at 16:15:15. Contact: ###-####. Part trap primers 8/2/00 12:01:26 PM
|
Groundwork | 8/1/2000 | 8/1/2000 | 8/1/2000 | P | PART |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 8/1/2000 fd primer lines central shop ar 8/1/2000 5:18:07 PM ea and nrth east area 8/1/2000 5:18:27 PM
|
Groundwork | 7/28/2000 | 7/31/2000 | 7/31/2000 | A | FAIL |
Lee Rice
|
|
|
Scheduled by a contractor via Hello! on 07/28/2000 at 14:26:06. Contact: ###-####. Edge of ditch to close to footing ok to cover except by footing, correction to consulte engineering on footing. 7/31/00 4:31:58 PM
|
Groundwork | 7/28/2000 | 7/28/2000 | 7/28/2000 | P | FAIL |
Lee Rice
|
|
|
Scheduled by a contractor via Hello! on 07/28/2000 at 10:57:57. Contact: ###-####. On job at 1:00 p.m. Not Ready.. Called Steve(Debest forman) later and asked him to call me if he got a test on and if I could I would make a trip back. No call came in by 4:45 p.m.
|
Groundwork | 7/12/2000 | 7/13/2000 | 7/12/2000 | A | PASS |
Lee Rice
|
|
|
Scheduled by a contractor via Hello! on 07/12/2000 at 11:55:42. Contact: ###-####. RWL- west wing 7/13/00 11:21:07 AM
|
Groundwork | 7/11/2000 | 7/11/2000 | 7/11/2000 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 07/11/2000 at 11:04:38. Contact: ###-####. east restroom, steamroom and eastern rd north side 7/11/00 2:49:24 PM
|
Groundwork | 7/7/2000 | 7/7/2000 | 7/7/2000 | P | PART |
Bill VanDegrift
|
|
|
###-#### partial groundwork late pm please restroom 7/7/00 2:31:59 PM
|
Groundwork | 7/6/2000 | 7/6/2000 | 7/6/2000 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 07/06/2000 at 08:34:48. Contact: ###-####. 1 restroom , break room, showers one restroom to go on the west side 7/6/00 2:02:42 PM
|
Groundwork | 7/5/2000 | 7/5/2000 | 7/5/2000 | P | FAIL |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 07/05/2000 at 10:48:21. Contact: ###-####. no test 7/5/00 2:06:44 PM
|
Water and/or Sewer | 5/22/2000 | 5/23/2000 | 5/23/2000 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 05/22/2000 at 13:29:22. Contact: ###-####. water service ok 5/23/00 9:57:21 AM
|
Water and/or Sewer | 5/18/2000 | 5/18/2000 | 5/18/2000 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 05/18/2000 at 10:27:51. Contact: ###-####. water line stubout only 5/19/00 8:17:42 AM
|
Application received | | | 5/17/2000 | | |
|
|
|
|
Issue & PRINT FEE-DUE permit | | | 5/17/2000 | | DONE |
|
|
|
|