Telephone call | | | 1/11/2002 | | DONE |
|
|
|
|
PLM-Aging Inspection | 8/27/2001 | 8/27/2001 | 8/27/2001 | | PASS |
Gerry Varner
|
|
|
|
DOC - Permit Finaled | 8/27/2001 | 8/27/2001 | 8/27/2001 | P | PASS |
Gerry Varner
|
|
|
Finaled by inspector at 8/27/2001 1:00:06 PM
|
Final | 6/25/2001 | 6/26/2001 | 6/26/2001 | A | PASS |
Gerry Varner
|
|
|
Scheduled by Inspector: 309 On 6/25/2001 4:08:19 PM
|
Final | 6/25/2001 | 6/25/2001 | 6/25/2001 | P | CANC |
Lee Rice
|
|
|
Scheduled by a contractor via Hello! on 06/25/2001 at 07:34:15. Contact: ###-####.couldn't get too it today, had Jerry call them to let know and I will reschedule for tomarrow. 6/25/2001 4:10:09 PM
|
Final | 6/21/2001 | 6/22/2001 | 6/22/2001 | A | PART |
Gerry Varner
|
|
|
Scheduled by a contractor via Hello! on 06/21/2001 at 21:29:24. Contact: ###-####. temp occ. only 6/22/2001 1:48:12 PM
|
Plumbing Rough-in | 5/14/2001 | 5/15/2001 | 5/15/2001 | P | PASS |
Gerry Varner
|
|
|
Scheduled by a contractor via Hello! on 05/14/2001 at 20:03:54. Contact: ###-####.
|
Groundwork | 4/12/2001 | 4/12/2001 | 4/12/2001 | P | FAIL |
Lee Rice
|
|
|
###-#### not enough grade on pipes in several places. test not on yet. 4/12/2001 3:05:32 PM
|
Groundwork | 4/12/2001 | 4/12/2001 | 4/12/2001 | P | FAIL |
Lee Rice
|
|
|
Scheduled by Inspector: 309 On 4/12/2001 3:04:02 PM Gave ok on waste, but need approval letter from engineer on underslap copper water piping, could not find where it showed that way on plan. 4/12/2001 5:17:51 PM
|
Application received | | | 4/12/2001 | | |
|
|
|
|
Issue & PRINT permit | | | 4/12/2001 | | DONE |
|
|
|
|