Final | 11/29/2001 | 12/3/2001 | 12/3/2001 | A | FAIL |
Stan Johnson
|
|
|
###-#### ext 204\\stan will you check on this for additional fixtures this permit only has a sewer line and he says you did the rough in and now he wants the final???? I didn't do a rough in he stubed sewer into building so he could rough in later decided to rough it i9n now and leave finish till later will buy permits for future fixtures on 10-04-01 he told me looked at water test ok 12/3/2001 2:18:13 PM
|
Plumbing Rough-in | 12/3/2001 | 12/3/2001 | 12/3/2001 | P | PART |
Stan Johnson
|
|
|
Scheduled by Inspector: 352 On 12/3/2001 2:19:37 PM water test ok will buy fixture permits 1 wc 1sho 1 lav 1aundry sink 1 water heater 12/3/2001 2:22:32 PM
|
Water and/or Sewer | 9/13/2001 | 9/17/2001 | 9/17/2001 | A | PASS |
Stan Johnson
|
|
|
###-#### ext. 204 Del Motz
|
DOC - Permit Finaled | 9/17/2001 | 9/17/2001 | 9/17/2001 | A | PASS |
Stan Johnson
|
|
|
Finaled by inspector at 9/17/2001 11:23:43 AM
|
Water and/or Sewer | 7/2/2001 | 7/6/2001 | 7/6/2001 | P | PART |
Stan Johnson
|
|
|
###-#### line ran and tested 10 foot from building turned up in wall for future bathroom upstairs will hookup in front of house later 7/6/2001 1:59:55 PM
|
Application received | | | 6/11/2001 | | |
|
|
|
|
Issue & PRINT permit | | | 6/11/2001 | | DONE |
|
|
|
|