Telephone Call | | | 11/25/2002 | | DONE |
|
|
|
|
Final | 3/6/2002 | 3/7/2002 | 3/7/2002 | P | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 03/06/2002 at 14:20:37. Contact: ###-####.
|
DOC - Permit Finaled | 3/7/2002 | 3/7/2002 | 3/7/2002 | P | PASS |
Jim Johnson
|
|
|
Finaled by inspector at 3/7/2002 3:58:04 PM
|
Final | 3/5/2002 | 3/6/2002 | 3/6/2002 | A | NR |
Jim Johnson
|
|
|
###-####
|
Plumbing Rough-in | 2/12/2002 | 2/13/2002 | 2/13/2002 | A | PART |
Jim Johnson
|
|
|
###-#### up date water distribution to new bathroom,s . relocate expansion tank to cold water side of water heater. repipe T&P line. provide approved type hose bibb,s to out side of building . repipe kit sink vent through roof. have D.C. tested and certified . it,s ok to cover floor and wall,s only for new bathroom,s 2/13/2002 3:09:02 PM
|
Plumbing Rough-in | 2/12/2002 | 2/12/2002 | 2/12/2002 | P | CANC |
Jim Johnson
|
|
|
MARY ###-#### cancel per Mary with Terrell Plumbing
|
Application received | | | 2/11/2002 | | |
|
|
|
|
Issue permit | | | 2/11/2002 | | DONE |
|
|
|
|