Telephone Call | | | 12/2/2002 | | DONE |
|
|
|
|
DOC - Permit Finaled | 6/19/2002 | 6/19/2002 | 6/19/2002 | A | PASS |
Bill VanDegrift
|
|
|
Finaled by inspector at 6/19/2002 8:44:01 AM
|
Final | 6/18/2002 | 6/18/2002 | 6/18/2002 | P | PASS |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 06/18/2002 at 10:52:13. Contact: ###-####.
|
Final | 6/13/2002 | 6/14/2002 | 6/14/2002 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 06/13/2002 at 15:10:09. Contact: ###-####. dcva required on ice mech, seal around floor sink in wait station, temp occ ok 6/14/2002 2:49:00 PM
|
Final | 5/24/2002 | 5/28/2002 | 5/28/2002 | A | NR |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 05/24/2002 at 09:11:57. Contact: ###-####. set all equipment, ice mech., coffee makers, etc., test all backflow preventors, seal around the floor sink in the wait station up front. 5/28/2002 9:11:33 AM
|
Plumbing Rough-in | 4/11/2002 | 4/12/2002 | 4/12/2002 | A | PASS |
Bill VanDegrift
|
|
|
Scheduled by Inspector: 330 On 4/11/2002 10:07:28 AM check interceptor and water system interceptor test ok ri complete ok 4/12/2002 9:54:08 AM
|
Plumbing Rough-in | 4/10/2002 | 4/11/2002 | 4/11/2002 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 04/10/2002 at 13:23:54. Contact: ###-####. waste and vent system ok 4/11/2002 10:07:46 AM
|
Plumbing Rough-in | 4/5/2002 | 4/8/2002 | 4/8/2002 | A | PASS |
Gary Ziegler
|
|
|
Scheduled by a contractor via Hello! on 04/05/2002 at 15:03:03. Contact: ###-####.
|
Application received | | | 4/2/2002 | | |
|
|
|
|
Issue & PRINT permit | | | 4/2/2002 | | DONE |
|
|
|
|