Final | 10/28/2002 | 10/28/2002 | 10/28/2002 | P | PASS |
Bill VanDegrift
|
|
|
###-#### sterling construction installed a sprinkler system for this place, the tie in seems ok but the dcva needs testing and they need a permit, didnt want to hold up this project final ok 10/28/2002 3:16:14 PM
|
DOC - Permit Finaled | 10/28/2002 | 10/28/2002 | 10/28/2002 | P | PASS |
Bill VanDegrift
|
|
|
Finaled by inspector at 10/28/2002 3:16:17 PM
|
Final | 10/24/2002 | 10/24/2002 | 10/24/2002 | P | PART |
Ron Ginner
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung no air gap on two t&p drains from water heaters. 10/25/2002 1:07:21 AM
|
Water and/or Sewer | 10/21/2002 | 10/21/2002 | 10/21/2002 | P | PASS |
Bill VanDegrift
|
|
|
###-#### water line ok to cover when bedded in the clean fill out back instead of the clods around the trench 10/21/2002 2:10:58 PM
|
Plumbing Rough-in | 8/27/2002 | 8/27/2002 | 8/27/2002 | P | PASS |
Bill VanDegrift
|
|
|
###-#### LEE this is an addition, the requirement for backwater valves is for new construction per boise city plumbing code inforcement practices, ri ok 8/27/2002 2:36:52 PM
|
Plumbing Rough-in | 8/26/2002 | 8/26/2002 | 8/26/2002 | P | FAIL |
Lee Rice
|
|
|
lee; Phone #: ###-#### couldn't find backwater valve, no notes on partial G/w.??? 8/26/2002 3:39:29 PM
|
Plumbing Rough-in | 7/25/2002 | 7/25/2002 | 7/25/2002 | P | PART |
Bill VanDegrift
|
|
|
LEE ###-#### gwok 7/25/2002 3:14:55 PM
|
Application received | | | 7/25/2002 | | |
|
|
|
|
Issue & PRINT permit | | | 7/25/2002 | | DONE |
|
|
|
|