Telephone Call | | | 6/30/2003 | | DONE |
|
|
|
|
DOC - Permit Finaled | 12/16/2002 | 12/16/2002 | 12/16/2002 | P | PASS |
Jim Johnson
|
|
|
Finaled by inspector at 12/16/2002 4:09:30 PM
|
Final | 12/13/2002 | 12/16/2002 | 12/16/2002 | A | PASS |
Jim Johnson
|
|
|
matt ###-####
|
Final | 12/13/2002 | 12/13/2002 | 12/13/2002 | P | PART |
Jim Johnson
|
|
|
MATT ###-#### need to have P.B.V. and double check tested and certified for final 12/13/2002 3:56:32 PM
|
Final | 12/10/2002 | 12/10/2002 | 12/10/2002 | P | PART |
Jim Johnson
|
|
|
###-#### need to install a pvb for mat washing unit and a double check for steam table oked temp 12/11/2002 12:23:45 PM
|
Plumbing Rough-in | 11/6/2002 | 11/6/2002 | 11/6/2002 | P | PASS |
Jim Johnson
|
|
|
as late as possible\\###-####
|
Roof Drains | 10/31/2002 | 10/31/2002 | 10/31/2002 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 10/31/2002 at 02:14:35. Contact: ###-####. need to fix leak and retest on north east over flow roof drain 10/31/2002 1:42:39 PM
|
Groundwork | 9/30/2002 | 9/30/2002 | 9/30/2002 | A | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 09/30/2002 at 07:13:19. Contact: ###-####.
|
Application received | | | 9/26/2002 | | |
|
|
|
|
Issue & PRINT permit | | | 9/26/2002 | | |
|
|
|
|