Final | 7/24/2003 | 7/25/2003 | 7/25/2003 | A | PASS |
Gary Ziegler
|
|
|
Scheduled by a contractor via Hello! on 7/24/2003 at 1:27:40 PM. Contact: ###-####.
|
DOC - Permit Finaled | 7/25/2003 | 7/25/2003 | 7/25/2003 | P | PASS |
Gary Ziegler
|
|
|
Finaled by inspector at 7/25/2003 12:48:22 PM
|
Plumbing Rough-in | 2/24/2003 | 2/24/2003 | 2/24/2003 | P | PASS |
Gary Ziegler
|
|
|
Scheduled by a contractor via Hello! on 2/24/2003 at 8:43:13 AM. Contact: ###-####.
|
Plumbing Rough-in | 2/20/2003 | 2/21/2003 | 2/21/2003 | A | FAIL |
Gary Ziegler
|
|
|
Scheduled by a contractor via Hello! on 2/20/2003 at 2:27:31 PM. Contact: ###-####.
|
Plumbing Rough-in | 2/20/2003 | 2/20/2003 | 2/20/2003 | P | NR |
Gary Ziegler
|
|
|
Scheduled by a contractor via Hello! on 2/20/2003 at 9:38:02 AM. Contact: ###-####.
|
Groundwork | 1/14/2003 | 1/14/2003 | 1/14/2003 | P | PASS |
Gary Ziegler
|
|
|
Scheduled by a contractor via Hello! on 01/14/2003 at 07:58:42. Contact: ###-####.
|
Application received | | | 1/13/2003 | | |
|
|
|
|
Issue & PRINT permit | | | 1/13/2003 | | |
|
|
|
|