Third Notice PLM | 3/1/2005 | 3/1/2005 | 3/14/2005 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Third Notice PLM | 3/1/2005 | 3/1/2005 | 3/14/2005 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice PLM | 2/10/2005 | 2/10/2005 | 3/1/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
Second Notice PLM | 2/10/2005 | 2/10/2005 | 3/1/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice Sent | | 1/18/2005 | 2/10/2005 | | DONE |
|
|
|
|
First Notice Sent | | 1/18/2005 | 2/10/2005 | | DONE |
|
|
|
|
DOC - Permit Finaled | 1/18/2005 | 1/18/2005 | 1/18/2005 | A | PASS |
Gary Ziegler
|
|
|
Finaled by inspector at 1/18/2005 8:23:59 AM
|
Final | 1/18/2005 | 1/18/2005 | 1/18/2005 | A | PASS |
Gary Ziegler
|
|
|
|
Final | 1/17/2005 | 1/18/2005 | 1/18/2005 | A | PASS |
Gary Ziegler
|
|
|
Scheduled by a contractor via Hello! on 1/17/2005 at 9:57:28 AM. Contact: ###-####.
|
DOC - Permit Finaled | 1/18/2005 | 1/18/2005 | 1/18/2005 | A | PASS |
Gary Ziegler
|
|
|
Finaled by inspector at 1/18/2005 10:58:29 AM
|
Final | 11/24/2004 | 11/24/2004 | 11/24/2004 | P | CANC |
Gary Ziegler
|
|
|
Scheduled by a contractor via Hello! on 11/24/2004 at 10:31:49 AM. Contact: ###-####.
|
Plumbing Rough-in | 11/24/2004 | 11/24/2004 | 11/24/2004 | P | PASS |
Gary Ziegler
|
|
|
|
Other | 11/4/2004 | 11/5/2004 | 11/5/2004 | A | PASS |
Gerry Varner
|
|
|
Eric-Conference requested ; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner
|
Application received | | | 11/4/2004 | | |
|
|
|
|
Issue permit | | | 11/4/2004 | | DONE |
|
|
|
|