Third Notice PLM | 8/27/2005 | 8/27/2005 | 9/7/2005 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Third Notice PLM | 8/10/2005 | 8/10/2005 | 9/7/2005 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice PLM | 8/10/2005 | 8/10/2005 | 8/27/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
Second Notice PLM | 7/25/2005 | 7/25/2005 | 8/10/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 7/22/2005 | 7/22/2005 | 8/10/2005 | | DONE |
Bill VanDegrift
|
|
|
|
First Notice | 6/30/2005 | 6/30/2005 | 7/25/2005 | | DONE |
Bill VanDegrift
|
|
|
|
Final | 7/22/2005 | 7/22/2005 | 7/22/2005 | P | PASS |
Bill VanDegrift
|
|
|
final ok again
|
Plumbing Rough-in | 7/5/2005 | 7/5/2005 | 7/5/2005 | P | NR |
Bill VanDegrift
|
|
|
per your request , this permit got finaled in error. the cabinet that was installed at the time of the inspection was the wrong one, per Jim Story, it will require a final inspection when the perminant cabinet is installed.
|
CHANGE STATUS TO (I) | | | 7/5/2005 | | DONE |
|
|
|
Per Bill VandeGrift please re-open///7/5/05 10:05am BAS
|
Final | 6/29/2005 | 6/30/2005 | 6/30/2005 | P | PASS |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 6/29/2005 at 6:07:23 PM. Contact: ###-####. final ok
|
Plumbing Rough-in | 6/8/2005 | 6/8/2005 | 6/8/2005 | P | PASS |
Bill VanDegrift
|
|
|
bob ###-#### job super says no core drilling slab for structural reasons, pump ok. ri ok
|
Application received | | | 6/8/2005 | | |
|
|
|
|
Issue & PRINT permit | | | 6/8/2005 | | DONE |
|
|
|
|