Third Notice PLM | 6/2/2006 | 6/2/2006 | 6/14/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice PLM | 5/2/2006 | 5/2/2006 | 6/2/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 4/11/2006 | 4/11/2006 | 5/2/2006 | | DONE |
Jim Johnson
|
|
|
|
Final | 4/10/2006 | 4/11/2006 | 4/11/2006 | A | PASS |
Jim Johnson
|
|
|
paul; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Final | 2/23/2006 | 2/24/2006 | 2/24/2006 | A | PART |
Jim Johnson
|
|
|
Paul; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong oked temp
|
Final | 2/8/2006 | 2/9/2006 | 2/9/2006 | A | NR |
Jim Johnson
|
|
|
wants temp occ.//jerry; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa not ready
|
PLM-Aging Inspection | 1/23/2006 | 1/23/2006 | 1/23/2006 | | PASS |
Jim Johnson
|
|
|
still working on project
|
PLM-Aging Inspection | 11/21/2005 | 11/21/2005 | 11/21/2005 | | PASS |
Jim Johnson
|
|
|
still working on project
|
Plumbing Rough-in | 9/18/2005 | 9/19/2005 | 9/19/2005 | P | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 9/18/2005 at 5:19:12 PM.
|
Groundwork | 8/15/2005 | 8/15/2005 | 8/15/2005 | P | PASS |
Jim Johnson
|
|
|
jerry ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
Application received | | | 7/1/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/1/2005 | | |
|
|
|
|