Second Notice PLM | 10/4/2007 | 10/4/2007 | 10/17/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 8/29/2007 | 8/29/2007 | 10/4/2007 | | DONE |
Eric Strole
|
|
|
|
Final | 8/28/2007 | 8/29/2007 | 8/29/2007 | A | PASS |
Eric Strole
|
|
|
|
Water and/or Sewer | 8/28/2007 | 8/29/2007 | 8/28/2007 | A | CANC |
Eric Strole
|
|
|
Please inspect for final at D-wing. Phone #: ###-#### Internet Inspection Request from: Carl Homola
|
Final | 8/22/2007 | 8/23/2007 | 8/23/2007 | A | PART |
Eric Strole
|
|
|
Please inspect final for D-wing. Thanks. Phone #: ###-#### Internet Inspection Request from: Carl Homola-need to install hbv's on boiler bibs in mech room. need all fixtures installed. temp ok.
|
PLM-Aging Inspection | 8/3/2007 | 8/3/2007 | 8/3/2007 | | NR |
Eric Strole
|
|
|
wip
|
Other | 5/31/2007 | 6/1/2007 | 6/1/2007 | A | DONE |
Eric Strole
|
|
|
Please see foreman for consultation in D-wing. Thank you. Phone #: ###-#### Internet Inspection Request from: Carl Homola-this was a conferance on running a drain for a dishwasher in a island, will run drain in drop ceiling to kitchen sink.
|
Plumbing Rough-in | 5/17/2007 | 5/17/2007 | 5/17/2007 | P | PASS |
Eric Strole
|
|
|
d-wing rough-in complete.
|
Plumbing Rough-in | 5/16/2007 | 5/17/2007 | 5/17/2007 | A | PART |
Eric Strole
|
|
|
missing some nail plates, isolators, supports on pex, curved pex stub outs & 1/2" copper line in w/h room.
|
Plumbing Rough-in | 5/16/2007 | 5/16/2007 | 5/16/2007 | P | PART |
Eric Strole
|
|
|
Please inspect partial D-wing rough-in. Thankyou. Phone #: ###-#### Internet Inspection Request from: Carl Homola-all dwv in d-wing pass.all roof drains pass.
|
Plumbing Rough-in | 5/14/2007 | 5/15/2007 | 5/15/2007 | P | CANC |
Eric Strole
|
|
|
Please inspect partial D-wing rough-in. Thankyou. Phone #: ###-#### Internet Inspection Request from: Carl Homola
|
Water and/or Sewer | 5/11/2007 | 5/11/2007 | 5/11/2007 | P | NR |
Eric Strole
|
|
|
Please inspect partial D-wing this afternoon if possible. Thankyou. Phone #: ###-#### Internet Inspection Request from: Carl Homola
|
Plumbing Rough-in | 5/9/2007 | 5/10/2007 | 5/10/2007 | P | PART |
Eric Strole
|
|
|
Please inspect partial D-wing rough-in. Thankyou. Phone #: ###-#### Internet Inspection Request from: Carl Homola-2nd leg d-wing dwv pass- all roof drains d-wing pass.
|
Plumbing Rough-in | 5/8/2007 | 5/9/2007 | 5/9/2007 | A | PART |
Eric Strole
|
|
|
Please inspect partial D-wing top-out. Thankyou. Phone #: ###-#### Internet Inspection Request from: Carl Homola-1st leg of d-wing dwv pass.
|
PLM-Aging Inspection | 4/24/2007 | 4/24/2007 | 4/24/2007 | | NR |
Eric Strole
|
|
|
wip
|
Water and/or Sewer | 2/21/2007 | 2/22/2007 | 2/22/2007 | A | PART |
Bill VanDegrift
|
|
|
Please inspect riser room rough-in (near D-wing). Thanks. Phone #: ###-####added rain drain riser between area B andC and relocated 6" p-trap in fire riser room. ok.
|
Groundwork | 1/11/2007 | 1/12/2007 | 1/12/2007 | A | PART |
Eric Strole
|
|
|
3" grease line under electrical room & stub out to intersepter ok to cover,still needs to air test under slab work as per conversation with jason & job forman.
|
Plumbing Rough-in | 1/11/2007 | 1/11/2007 | 1/11/2007 | P | PART |
Eric Strole
|
|
|
Please inspect D-wing underground - will be ready at 10 or 11 AM if you''re available. Thank you! Phone #: ###-####-need to bed ground work & test.
|
PLM-Aging Inspection | 12/5/2006 | 12/5/2006 | 12/5/2006 | | NR |
Eric Strole
|
|
|
wip
|
Groundwork | 10/5/2006 | 10/5/2006 | 10/5/2006 | P | PASS |
Eric Strole
|
|
|
Please inspect partial underground of D-wing this afternoon. Thanks!; Phone #: ###-#### Internet Inspection Request from: Carl Homola-D building ground work complete.
|
Groundwork | 10/3/2006 | 10/3/2006 | 10/3/2006 | P | PART |
Eric Strole
|
|
|
the east & north end ground work ok.
|
Groundwork | 9/29/2006 | 9/29/2006 | 9/29/2006 | P | CANC |
Eric Strole
|
|
|
|
Groundwork | 9/29/2006 | 9/29/2006 | 9/29/2006 | A | FAIL |
Eric Strole
|
|
|
change out 8x4 pvc y,a pvc patch is not approved to fix hole in fitting-change mission bands to no-hub or fernco-test ground work-remove rocks in trench.
|
Groundwork | 9/20/2006 | 9/20/2006 | 9/20/2006 | P | PART |
Eric Strole
|
|
|
A wing ground work complete.
|
Plumbing Rough-in | 9/20/2006 | 9/20/2006 | 9/20/2006 | P | CANC |
Eric Strole
|
|
|
Please inspect partial A-wing underslab.; Phone #: ###-#### Internet Inspection Request from: Carl Homola
|
Plumbing Rough-in | 9/19/2006 | 9/20/2006 | 9/20/2006 | A | PART |
Jim Johnson
|
|
|
Please inspect parital A-wing underground tomorrow AM; Phone #: ###-#### Internet Inspection Request from: Carl Homola need to correct leak in Y at end of line clean out and retest
|
Groundwork | 9/12/2006 | 9/13/2006 | 9/13/2006 | P | PART |
Eric Strole
|
|
|
Please inspect partial underslab A/B-wing. Thanks.; Phone #: ###-#### Internet Inspection Request from: Carl Homola-east end a building ground work ok.
|
Application received | | | 9/11/2006 | | |
|
|
|
|
Issue permit | | | 9/11/2006 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/11/2006 | | DONE |
|
|
|
|
Third Notice PLM | 10/17/2007 | 10/17/2007 | | | |
|
|
|
Second Notice has not been responded to.
|