Third Notice PLM | 8/16/2007 | 8/16/2007 | 9/14/2007 | | DONE |
|
|
|
This permit finaled on the web by Heidi Mallet
|
Second Notice PLM | 7/23/2007 | 7/23/2007 | 8/16/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 5/10/2007 | 5/10/2007 | 7/23/2007 | | DONE |
Jim Johnson
|
|
|
|
Final | 5/9/2007 | 5/10/2007 | 5/10/2007 | A | PASS |
Jim Johnson
|
|
|
Sean Hart is the field contact. Need final Inspection for temp water line to job trailer. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet
|
Groundwork | 4/25/2007 | 4/25/2007 | 4/25/2007 | P | PASS |
Jim Johnson
|
|
|
Jim Henderson is the field contact Phone #: ###-#### Internet Inspection Request from: Heidi Mallet new water to job trailer test ok need to have water company tutn water on so double check for job trailer premius protection can be tested and certified
|
Application received | | | 4/24/2007 | | DONE |
|
|
|
This permit was created on the web by Heidi Mallet
|