CHANGE STATUS TO (COL) | | | 1/18/2008 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/25/2007 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/25/2007 | | |
|
|
|
|
Plumbing Rough-in | 9/26/2007 | 9/26/2007 | 9/26/2007 | P | PASS |
Eric Strole
|
|
|
steve Phone #: ###-#### cell ###-####
|
Plumbing Rough-in | 9/21/2007 | 9/21/2007 | 9/21/2007 | P | FAIL |
Eric Strole
|
|
|
dwv test failed, reinspection fee issued.
|
Plumbing Rough-in | 9/18/2007 | 9/19/2007 | 9/19/2007 | A | FAIL |
Eric Strole
|
|
|
dwv test failed.
|
Plumbing Rough-in | 9/18/2007 | 9/18/2007 | 9/18/2007 | P | NH |
Eric Strole
|
|
|
steve Phone #: ###-####
|
Plumbing Rough-in | 9/12/2007 | 9/13/2007 | 9/13/2007 | A | FAIL |
Eric Strole
|
|
|
steve Phone #: ###-####-replace all fittings on dwv that have been siliconed, test all new dwv, fix reverse grade in crawl, if fail on next inspection a reinspection fee will be issued.
|
Plumbing Rough-in | 9/7/2007 | 9/10/2007 | 9/10/2007 | A | FAIL |
Eric Strole
|
|
|
steve Phone #: ###-####-test dwv,remove galvanized cap on copper male adaptor & use approved material, remove stops on tub & replumb, replace tub drain, fix reverse grade on overhead vent & support dwv every 4'.
|
Plumbing Rough-in | 8/24/2007 | 8/24/2007 | 8/24/2007 | P | FAIL |
Daryl Spivey
|
|
|
removed R/I approved sticker for work done after inspection...correction notice on site. shower valve needs reinstalled, remove section of 3" drain on washer, replace all fittings in crawl that was sliconed and or caulked, support waste, vent and water per code, replace pvc section of tub drain, replumb tub valve.......ds
|
Other | 8/24/2007 | 8/24/2007 | 8/24/2007 | P | DONE |
Eric Strole
|
|
|
turned it over to dayrl.
|
Plumbing Rough-in | 8/2/2007 | 8/2/2007 | 8/2/2007 | P | PASS |
Daryl Spivey
|
|
|
|
Other | 7/10/2007 | 7/11/2007 | 7/11/2007 | A | PASS |
Daryl Spivey
|
|
|
steve - conference Phone #: ###-####
|
Application received | | | 6/18/2007 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/18/2007 | | DONE |
|
|
|
|