First Notice | 11/20/2008 | 11/20/2008 | 2/24/2009 | | DONE |
Eric Strole
|
|
|
|
Final | 11/19/2008 | 11/20/2008 | 11/20/2008 | P | PASS |
Eric Strole
|
|
|
|
Final | 11/19/2008 | 11/19/2008 | 11/19/2008 | P | PART |
Eric Strole
|
|
|
need to finish all trim & get usc information on svb
|
Final | 11/18/2008 | 11/19/2008 | 11/19/2008 | A | PART |
Eric Strole
|
|
|
need to install dbca on ice maker & finish all trim.
|
Final | 11/18/2008 | 11/18/2008 | 11/18/2008 | P | PART |
Eric Strole
|
|
|
Attempting plumbing final inspection. May be missing cabinet for salon sink, but we are told it should be installed. Phone #: ###-#### Internet Inspection Request from: JASON MEANS-need to finish all trim. temp final ok
|
Final | 11/14/2008 | 11/14/2008 | 11/14/2008 | P | PART |
Eric Strole
|
|
|
this was a wolk thru.
|
Final | 11/12/2008 | 11/12/2008 | 11/12/2008 | P | PART |
Jim Johnson
|
|
|
partial final made walk through with Bob not ready still installing fixtures
|
Final | 11/5/2008 | 11/6/2008 | 11/6/2008 | P | PART |
Eric Strole
|
|
|
partial final-north & east wing complete. need drinking fountains, kitchen & all kitchen equipment installed, laundry room & med room complete & waterheaters fired.
|
Sprinkler (Final) | 9/25/2008 | 9/25/2008 | 9/25/2008 | P | PART |
Bill VanDegrift
|
|
|
tie in for two fountains ok rp's need testing
|
Plumbing Rough-in | 9/22/2008 | 9/23/2008 | 9/23/2008 | A | PASS |
Jim Johnson
|
|
|
tenting of overhead waterlines.
|
Plumbing Rough-in | 9/22/2008 | 9/22/2008 | 9/22/2008 | P | CANC |
Eric Strole
|
|
|
|
Plumbing Rough-in | 9/22/2008 | 9/22/2008 | 9/22/2008 | A | PART |
Eric Strole
|
|
|
tenting-tenting not complete.
|
Plumbing Rough-in | 9/11/2008 | 9/11/2008 | 9/11/2008 | A | PART |
Eric Strole
|
|
|
showers & tenting-all showers are installed,there is still tenting to complete.
|
Other | 9/8/2008 | 9/8/2008 | 9/8/2008 | P | PASS |
Eric Strole
|
|
|
tubs in the north wing are complete.
|
Plumbing Rough-in | 8/29/2008 | 9/2/2008 | 9/2/2008 | P | PASS |
Eric Strole
|
|
|
2:00 pm-rough-in pass, ok to cover except showers. all shower units need to be installed. contractor to call when complete.
|
Plumbing Rough-in | 8/28/2008 | 8/29/2008 | 8/29/2008 | A | NR |
Eric Strole
|
|
|
11:00 am
|
Plumbing Rough-in | 8/28/2008 | 8/28/2008 | 8/28/2008 | P | CANC |
Eric Strole
|
|
|
2:00 pm
|
Plumbing Rough-in | 8/27/2008 | 8/28/2008 | 8/28/2008 | A | NR |
Eric Strole
|
|
|
9:30 am
|
Plumbing Rough-in | 8/27/2008 | 8/27/2008 | 8/27/2008 | P | CANC |
Eric Strole
|
|
|
2:00 pm please
|
Plumbing Rough-in | 8/26/2008 | 8/27/2008 | 8/27/2008 | A | PART |
Eric Strole
|
|
|
10:00 am-all dwv pass, need to finish nailplates, tenting of overhead waterlines & install hosebibs.
|
Plumbing Rough-in | 8/25/2008 | 8/26/2008 | 8/26/2008 | P | PART |
Eric Strole
|
|
|
2:00 pm-dwv east wing pass, water test in mech room pass.
|
Plumbing Rough-in | 8/25/2008 | 8/26/2008 | 8/26/2008 | A | PART |
Eric Strole
|
|
|
10:00 am-west wing pass.
|
Plumbing Rough-in | 8/25/2008 | 8/25/2008 | 8/25/2008 | P | PART |
Eric Strole
|
|
|
dwv north wing & flr sink in kitchen pass. test on all water, except mec room pass. still need more tenting on overhead waterlines.
|
Groundwork | 8/13/2008 | 8/13/2008 | 8/13/2008 | P | FAIL |
Eric Strole
|
|
|
this is for a flr sink that is added in kitchen for ice machine. cannot tie drain in upstream of island sink. ok to do running test on groundwork for flr sink.
|
Plumbing Rough-in | 8/7/2008 | 8/8/2008 | 8/8/2008 | P | FAIL |
Eric Strole
|
|
|
this will be for a partial rough in. Phone #: ###-#### Internet Inspection Request from: JASON MEANS-(this is for the wing on south side) dwv test failed, support dwv every 4', support pex every 32", fix all backgraded vents, finish tenting all overhead waterlines & secure all tenting.
|
Water and/or Sewer | 7/8/2008 | 7/9/2008 | 7/9/2008 | A | PASS |
Eric Strole
|
|
|
grease interceptor test-test on interceptor pass.
|
Water and/or Sewer | 7/7/2008 | 7/8/2008 | 7/8/2008 | A | PART |
Eric Strole
|
|
|
this will be for test on grease interceptor-this is the start of 24 hr test.
|
Groundwork | 7/2/2008 | 7/2/2008 | 7/2/2008 | A | PASS |
Eric Strole
|
|
|
ground work pass.
|
Groundwork | 6/30/2008 | 6/30/2008 | 6/30/2008 | P | PART |
Eric Strole
|
|
|
this was for the tie-in of the vent, test port & cleanout for the grease interceptor, slill need to run vent to building & test.
|
Groundwork | 6/27/2008 | 6/27/2008 | 6/27/2008 | P | PART |
Eric Strole
|
|
|
dwv on sanitary and grease pass except interceptor vent, cleanout & test port & baffels & test on interceptor, need waterlines that are going to be under slab.
|
Groundwork | 6/26/2008 | 6/27/2008 | 6/27/2008 | A | PART |
Eric Strole
|
|
|
ok to cover grease waste, will come back in after noon to check test, still need grease interceptor vent run.
|
Groundwork | 6/26/2008 | 6/26/2008 | 6/26/2008 | P | PART |
Eric Strole
|
|
|
test on dwv pass, ok to cover, still need to run grease waste.
|
Groundwork | 6/25/2008 | 6/26/2008 | 6/26/2008 | A | FAIL |
Eric Strole
|
|
|
need full size cleanouts on branch drains over 5'- vent needs to be downstream of fixtures-fix all backgrade & bed all piping-need to use an approved fixture fitting for back to back toitets-fix leak on dwv & retest.
|
Groundwork | 6/24/2008 | 6/25/2008 | 6/25/2008 | P | NR |
Eric Strole
|
|
|
Phone #: ###-#### Internet Inspection Request from: JASON MEANS
|
Application received | | | 6/24/2008 | | DONE |
|
|
|
This permit was created on the web by JASON MEANS
|