Case Summary (PLM) | | | 8/8/2016 | | DONE |
|
|
|
|
Final | 3/30/2009 | 3/30/2009 | 3/30/2009 | P | PASS |
Jim Johnson
|
|
|
ken Phone #: ###-#### note- no sign-off card on site
|
Final | 3/3/2009 | 3/3/2009 | 3/4/2009 | P | PART |
Jim Johnson
|
|
|
Ken Phone #: ###-#### the water purveyor, cross connection manual sixth edition ,and upc 2003 require the potable water system to be protected. Big O Tire is on the same water service as Burlington need to install a double check with expansion tank for thermol expansion need to isolate the two water outlet,s in shop area with an RP with signage over outlet,s need to repipe coffee maker with an RP no sign off card on site will ok temp.
|
Plumbing Rough-in | 2/3/2009 | 2/4/2009 | 2/4/2009 | A | PASS |
Jim Johnson
|
|
|
ken Phone #: ###-#### rough-in test ok note- premise protection to be installed prior to final and auxiliary building ( Big O Tire ) back flow protection to be addressed after cross connection survey with water purveyor
|
Groundwork | 1/23/2009 | 1/26/2009 | 1/26/2009 | A | PASS |
Jim Johnson
|
|
|
ken Phone #: ###-####
|
Application received | | | 1/23/2009 | | |
|
|
|
|
Issue permit | | | 1/23/2009 | | DONE |
|
|
|
|
First Notice | 3/30/2009 | 3/30/2009 | | | |
Jim Johnson
|
|
|
|