First Notice | 4/22/2010 | 4/22/2010 | 9/1/2010 | | DONE |
Daryl Spivey
|
|
|
|
Final | 4/22/2010 | 4/22/2010 | 4/22/2010 | P | PASS |
Daryl Spivey
|
|
|
|
Plumbing Rough-in | 4/22/2010 | 4/22/2010 | 4/22/2010 | A | PASS |
Daryl Spivey
|
|
|
All rough in was done previously and passed at an earlier date........Was a mix up on permit................ds
|
Water and/or Sewer | 4/21/2010 | 4/22/2010 | 4/22/2010 | A | CANC |
Daryl Spivey
|
|
|
Onsite contact is Corry Hazen, would like final inspection.....thanks Inspection requested from web by: Jane Amy Phone #: ###-####
|
Med/Gas Systems | 3/29/2010 | 3/30/2010 | 3/30/2010 | P | PART |
Daryl Spivey
|
|
|
Correy 24 hr test completed...........ds
|
Med/Gas Systems | 3/29/2010 | 3/29/2010 | 3/29/2010 | P | CANC |
Daryl Spivey
|
|
|
24 hr. pressure test follow up. On site contact is Corry. Inspection requested from web by: Jane Amy Phone #: ###-#### x100 correy called me and rescheduled for tomorrow......................ds
|
Med/Gas Systems | 3/26/2010 | 3/26/2010 | 3/26/2010 | P | PART |
Daryl Spivey
|
|
|
On site contact is Padraic @ ###-####. Med Gas rough-in. Will also need to schedule follow up on Monday 03/29/10 Inspection requested from web by: Jane Amy Phone #: ###-#### x100 start 24 hr test..........ds
|
Application received | | | 1/4/2010 | | DONE |
|
|
|
This permit was created on the web by Jane Amy
|