First Notice | 10/18/2011 | 10/18/2011 | 11/9/2011 | | DONE |
Jim Johnson
|
|
|
This permit finaled on the web by Allison Briggs
|
First Notice | 10/18/2011 | 10/18/2011 | 11/9/2011 | | DONE |
Jim Johnson
|
|
|
This permit finaled on the web by Allison Briggs
|
Final | 10/18/2011 | 10/18/2011 | 10/18/2011 | P | PASS |
Jim Johnson
|
|
|
Contact Cory Wessleman For Detailed Instructions. Repack Room - Put Vacuum Breaker On Faucet Phone #: ###-#### >> Inspection requested via web by Allison Briggs note sign off card not on site
|
Water and/or Sewer | 10/13/2011 | 10/14/2011 | 10/14/2011 | P | PART |
Jim Johnson
|
|
|
STEIN DIST. FINAL PLUMBING CONTACT CORY ###-####. Phone #: ###-#### >> Inspection requested via web by Allison Briggs need air gap on compartment sink,s in storeage area or provide backflow assemblies or backflow prevention methods on the two sink,s for final called contractor will recall when ready
|
Final | 10/10/2011 | 10/11/2011 | 10/11/2011 | A | CANC |
Bill VanDegrift
|
|
|
final at stein per mike wilson of mcalvain email. ###-#### Phone #: ###-#### >> Inspection requested via web by Allison Briggs not ready
|
Final | 10/7/2011 | 10/10/2011 | 10/7/2011 | A | CANC |
Jim Johnson
|
|
|
Contact Cory Wessleman For Details
###-#### Phone #: ###-#### >> Inspection requested via web by Allison Briggs Inspection cancelled from web by: Allison Briggs
|
Final | 9/7/2011 | 9/8/2011 | 9/8/2011 | A | PART |
Jim Johnson
|
|
|
final plumbing at steins call dave to schedule ###-#### Phone #: ###-#### >> Inspection requested via web by Allison Briggs main office area final ok need to finish trim in warehouse area contractor to call when ready
|
Plumbing Rough-in | 8/31/2011 | 8/31/2011 | 8/31/2011 | P | PART |
Jim Johnson
|
|
|
CONTACT DAVE PORTER - ###-#### ALSO NEED ROOF DRAIN INSPECTION AND A PORTION THAT IS FINAL Phone #: ###-#### >> Inspection requested via web by Allison Briggs roof drains and vent,s test ok made walk through on final portion with Dave need to complete trim
|
Plumbing Rough-in | 8/25/2011 | 8/26/2011 | 8/26/2011 | A | PART |
Jim Johnson
|
|
|
Plumbing rough in - call dave ###-####. Phone #: ###-#### >> Inspection requested via web by Allison Briggs warehouse repack area rough-in test ok
|
Plumbing Rough-in | 8/25/2011 | 8/26/2011 | 8/25/2011 | A | CANC |
Jim Johnson
|
|
|
rough in at Stein call Dave ###-####. Phone #: ###-#### >> Inspection requested via web by Allison Briggs Inspection cancelled from web by: Allison Briggs
|
Groundwork | 7/12/2011 | 7/13/2011 | 7/13/2011 | A | PASS |
Jim Johnson
|
|
|
stein dist. groundwork call Cory to schedule ###-#### Phone #: ###-#### >> Inspection requested via web by Allison Briggs
|
Groundwork | 7/6/2011 | 7/7/2011 | 7/7/2011 | A | PART |
Jim Johnson
|
|
|
underground inspection at stein, call cory to schedule ###-#### Phone #: ###-#### >> Inspection requested via web by Allison Briggs ground work for trench drains test ok ok to cover
|
Water and/or Sewer | 6/30/2011 | 6/30/2011 | 6/30/2011 | P | PART |
Jim Johnson
|
|
|
Contact Cory Wessleman ###-####. Inspection for The Remainder Of The Underground Waste. Phone #: ###-#### >> Inspection requested via web by Allison Briggs dwv drain piping from building to interceptor on south-east side of building test ok ok to cover
|
Plumbing Rough-in | 6/17/2011 | 6/20/2011 | 6/20/2011 | A | PART |
Jim Johnson
|
|
|
underground waste rough call cory ###-#### Phone #: ###-#### >> Inspection requested via web by Allison Briggs ground-work in middle section of building south side test ok ok to cover
|
Plumbing Rough-in | 6/7/2011 | 6/8/2011 | 6/8/2011 | P | PART |
Jim Johnson
|
|
|
plumbing rough in at Stein - schedule with Cory on site ###-#### Phone #: ###-#### >> Inspection requested via web by Allison Briggs rough-in on office area test ok
|
PLM-Aging Inspection | 4/26/2011 | 4/26/2011 | 4/27/2011 | | PASS |
Jim Johnson
|
|
|
|
Groundwork | 2/24/2011 | 2/24/2011 | 2/24/2011 | P | PART |
Jim Johnson
|
|
|
Contact Brian Means For Specific Questions. Underground Waste & Vent Phone #: ###-#### >> Inspection requested via web by Allison Briggs ground work on east side of building test ok
|
Application received | | | 2/23/2011 | | DONE |
|
|
|
This permit was created on the web by Allison Briggs
|