First Notice | 8/2/2012 | 8/2/2012 | 5/10/2013 | | DONE |
Eric Strole
|
|
|
This permit finaled on the web by Stacia Haumann
|
Final | 8/2/2012 | 8/2/2012 | 8/2/2012 | A | PASS |
Eric Strole
|
|
|
|
Final | 6/15/2012 | 6/18/2012 | 6/18/2012 | A | PART |
Eric Strole
|
|
|
vent for flr drain in fire room pass.
|
Final | 6/13/2012 | 6/14/2012 | 6/15/2012 | A | CANC |
Eric Strole
|
|
|
|
Water and/or Sewer | 6/13/2012 | 6/13/2012 | 6/13/2012 | P | PART |
Eric Strole
|
|
|
this was a test on 4" building drain serving fireroom flr drain.test ok.
|
Water and/or Sewer | 6/13/2012 | 6/14/2012 | 6/13/2012 | A | CANC |
Eric Strole
|
|
|
|
Final | 6/5/2012 | 6/5/2012 | 6/5/2012 | P | CANC |
Eric Strole
|
|
|
1:00 pm
|
PLM-Aging Inspection | 5/17/2012 | 5/17/2012 | 5/17/2012 | | PART |
Eric Strole
|
|
|
|
Final | 2/16/2012 | 2/16/2012 | 2/16/2012 | A | PART |
Eric Strole
|
|
|
overflow ring for roof drain is on primary and needs to be on overflow. need to run T&P and pan drain ,need to test sewer east side for fire riser room and complete all labeling. Temp final ok
|
Roof Drains | 1/17/2012 | 1/17/2012 | 1/17/2012 | P | PART |
Eric Strole
|
|
|
building 50 roof drains complete.
|
Plumbing Rough-in | 1/12/2012 | 1/12/2012 | 1/12/2012 | P | PART |
Eric Strole
|
|
|
sewer for bath and bath rough-in
|
Plumbing Rough-in | 12/15/2011 | 12/16/2011 | 12/16/2011 | A | PART |
Eric Strole
|
|
|
domestic water feeding tempered water and tempered water main test pass.(tie-in of domestic water from existing building to new building to be done by others)all piping needs labeled.
|
Plumbing Rough-in | 12/14/2011 | 12/15/2011 | 12/15/2011 | P | PART |
Eric Strole
|
|
|
sub fab temp water test pass.
|
Plumbing Rough-in | 12/14/2011 | 12/15/2011 | 12/14/2011 | A | CANC |
Eric Strole
|
|
|
|
Roof Drains | 12/9/2011 | 12/9/2011 | 12/9/2011 | P | PART |
Eric Strole
|
|
|
north two roof drains pass.
|
Roof Drains | 11/2/2011 | 11/2/2011 | 11/2/2011 | P | PART |
Eric Strole
|
|
|
test on roof drains for building 10 pass, ( need to switch rings on primary and overflow.)
|
Roof Drains | 10/11/2011 | 10/12/2011 | 10/12/2011 | P | PART |
Eric Strole
|
|
|
roof drains for the west mecanical mezz pass.
|
Roof Drains | 9/22/2011 | 9/22/2011 | 9/22/2011 | P | PART |
Eric Strole
|
|
|
roof drains for the link pass.
|
Roof Drains | 9/21/2011 | 9/22/2011 | 9/22/2011 | A | PART |
Eric Strole
|
|
|
tie in of roof drains to storm drain south west corner pass. roof drains need tested.
|
Other | 8/9/2011 | 8/9/2011 | 8/9/2011 | A | PART |
Bill VanDegrift
|
|
|
went over rain water terminations inside building west end, will need to go to s.s. or i.w., 1% on 4" waste south side ok.
|
Application received | | | 8/1/2011 | | DONE |
|
|
|
This permit was created on the web by Stacia Haumann
|